17353 W GRESHAM ST 91325
Certificate Information: 17353 W GRESHAM ST 91325
- Application / Permit
- 20010-20000-04864
- Plan Check / Job No.
- B20VN16248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 51' X 33'-9" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A 33(c) and (d) . ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLRED REQUIRED THRU-OUT.
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 10/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | PARISA ZAHABI |
| Corrections Issued | 1/9/2021 | PARISA ZAHABI |
| Quality Review Completed | 1/27/2021 | OMID HEDAYAT |
| Plan Check Approved | 11/4/2021 | PARISA ZAHABI |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| CofO in Progress | 10/16/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
| CofO Issued | 10/24/2025 | RUBEN SALAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/1/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 3/8/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 4/19/2021 | DANG NGUYEN |
| Construction near power lines | Cleared | 6/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/10/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/23/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/5/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/27/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 12/27/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Insulation | 12/27/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 12/27/2023 | Corrections Issued | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 12/27/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 12/27/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/29/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 12/29/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/6/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/6/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 9/6/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/6/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/6/2024 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 9/6/2024 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 9/6/2024 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/6/2024 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 9/6/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 9/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/13/2024 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 10/28/2024 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 1/15/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 1/15/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Wood Frame | 1/15/2025 | No Access for Inspection | JAVIER RAMOS JR |
| Insulation | 1/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/30/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 2/12/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 7/3/2025 | Partial Approval | MICHAEL CORTEZ |
| Sewer | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 8/27/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 8/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/14/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 10/14/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 10/14/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 10/14/2025 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/14/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 10/14/2025 | Approved | CHRISTOPHER ROJAS |