1039 E NOWITA PL 90291

Certificate Information: 1039 E NOWITA PL 90291

Application / Permit
20010-20000-04857
Plan Check / Job No.
B20VN16230
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (60'-1"x 30'-0") TWO-STORY SINGLE FAMILY DWELLING WITH ATTACHED COVER PATIO, WITH NFPA-13D AUTOMATIC FIRE SPRINKLER. WORK PER ENGINEER.
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
CofO Issued on 7/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 CHON CHIO KUO
Corrections Issued 12/21/2020 CHON CHIO KUO
Quality Review Completed 12/24/2020 STEVEN KIM
Building Plans Picked Up 12/30/2020 APPLICANT
Applicant returned to address corrections 5/12/2021 CHON CHIO KUO
Applicant returned to address corrections 5/13/2021 CHON CHIO KUO
Applicant returned to address corrections 11/18/2021 TROY DEGUZMAN
Plan Check Approved 11/23/2021 TROY DEGUZMAN
Plan Check Approved 11/23/2021 TROY DEGUZMAN
Issued 11/29/2021 APPLICANT
CofO in Progress 7/22/2022 DAVID FEILER
Permit Finaled 7/27/2022 DANIEL ORRANTE
CofO Issued 7/27/2022 DANIEL ORRANTE
Permit Finaled 7/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/11/2021 RAYMOND MUGAMBWA
Roof/Waste drainage to street Cleared 3/16/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 3/17/2021 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 4/21/2021 MATTHEW CRAIG
Specific Plan Cleared 8/19/2021 PEDRO AYALA
Low Impact Development Cleared 9/24/2021 ANDRES COVARRUBIAS

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/17/2021 Approved DAVID FEILER
Underground Mechanical 12/17/2021 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 12/20/2021 Approved DAVID FEILER
Footing/Foundation/Slab 12/20/2021 Partial Approval DAVID FEILER
Footing/Foundation/Slab 12/28/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Approved JOHN KAYON
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/1/2022 Partial Approval DAVID FEILER
HVAC-Rough 2/1/2022 Approved DAVID FEILER
PLUMBING-Rough 2/1/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Not Ready for Inspection DAVID FEILER
Shower Pan 2/10/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 2/22/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 2/22/2022 Approved ANDREW NAVE
Wood Frame 2/22/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 2/28/2022 Approved DAVID FEILER
ELECTRICAL-Rough 2/28/2022 Approved DAVID FEILER
Green Building Rough 2/28/2022 Approved DAVID FEILER
Insulation 2/28/2022 Approved DAVID FEILER
Interior/Exterior Lathing 2/28/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 2/28/2022 Approved DAVID FEILER
Drywall Nailing 3/4/2022 Approved DAVID FEILER
Gas Test 3/4/2022 Partial Approval DAVID FEILER
Gas Test 5/10/2022 Approved DAVID FEILER
Underground Mechanical 5/10/2022 Partial Approval DAVID FEILER
ELECTRICAL-Final 7/7/2022 Corrections Issued DAVID FEILER
HVAC-Final 7/7/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 7/7/2022 Approved DAVID FEILER
ELECTRICAL-Final 7/13/2022 Approved DAVID FEILER
Final 7/13/2022 Corrections Issued DAVID FEILER
Green Building Final 7/13/2022 Approved DAVID FEILER
HVAC-Final 7/13/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Approved DAVID FEILER
Service/Power Release 7/13/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 7/13/2022 Approved DAVID FEILER
Final 7/22/2022 OK to Issue CofO DAVID FEILER
Service/Power Release 7/22/2022 Approved DAVID FEILER