4987 N VINCENT AVE 90041
Certificate Information: 4987 N VINCENT AVE 90041
- Application / Permit
- 20010-20000-04848
- Plan Check / Job No.
- B20VN16192
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (22'-0"x 44'-9") DETACHED ACCESSORY DWELLING UNIT WITH ONE-ATT. CAR GARAGE PER GCS 65852.2 (e)(1)(B) and LAMC 12.22 A.33(c), (d) and (g), NFPA-13R FIRE SPRINKLER THROUHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | TROY DEGUZMAN |
| Corrections Issued | 12/26/2020 | TROY DEGUZMAN |
| Quality Review Completed | 12/30/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/31/2020 | APPLICANT |
| Plan Check Approved | 5/19/2021 | TROY DEGUZMAN |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 3/10/2023 | CRAIG VAUGHAN |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 12/29/2020 | TROY DEGUZMAN |
| Address approval | Cleared | 2/4/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 2/22/2021 | TROY DEGUZMAN |
| Sewer availability | Cleared | 3/12/2021 | PAMELA TENEZA |
| Hydrant and Access approval | Cleared | 3/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/7/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/13/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/20/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 2/7/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 2/7/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/7/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 3/29/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 4/5/2022 | Approved | CHARLES BOGHOSKHAN |
| Green Building Rough | 4/5/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 4/12/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/1/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/2/2023 | Approved | CRAIG VAUGHAN |
| Green Building Final | 2/2/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 2/2/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/10/2023 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 2/10/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 2/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 2/10/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/9/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/9/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/9/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 3/9/2023 | Approved | CRAIG VAUGHAN |