4210 N KRAFT AVE 91604
Certificate Information: 4210 N KRAFT AVE 91604
- Application / Permit
- 20010-20000-04846
- Plan Check / Job No.
- B20VN16190
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (58'-11"x 39'-0") TWO-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | TROY DEGUZMAN |
| Corrections Issued | 1/12/2021 | TROY DEGUZMAN |
| Quality Review Completed | 1/13/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| Applicant returned to address corrections | 1/28/2021 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 8/4/2021 | TROY DEGUZMAN |
| Plan Check Approved | 8/9/2021 | TROY DEGUZMAN |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 6/8/2022 | DAVID MATSON |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 1/12/2021 | TROY DEGUZMAN |
| Address approval | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Highway dedication | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Permit | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/10/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 3/22/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 5/20/2021 | JOHN KIM |
| Low Impact Development | Cleared | 6/16/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/17/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grabarek,, Jaroslaw; Lic. No.: L9258 | 668 TWIN PEAKS AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/31/2021 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/10/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/21/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/19/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/26/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/26/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 10/26/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/28/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 10/29/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 11/3/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/3/2021 | Partial Approval | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 11/3/2021 | Approved | THOMAS FINNILA |
| Insulation | 11/8/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/12/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/12/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/23/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 2/23/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Final | 2/23/2022 | Approved | ARAM AVEDISIAN |
| Final | 2/25/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/25/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | THOMAS FINNILA |
| HVAC-Final | 3/15/2022 | Approved | ARAM AVEDISIAN |
| Final | 3/30/2022 | Conditional Approval | MATT KELLERMAN |
| Green Building Final | 3/30/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 3/30/2022 | Approved | MATT KELLERMAN |
| Smoke Detectors | 3/30/2022 | Approved | MATT KELLERMAN |
| Final | 6/7/2022 | OK to Issue CofO | DAVID MATSON |