4248 N RHODES AVE 91604

Certificate Information: 4248 N RHODES AVE 91604

Application / Permit
20010-20000-04795
Plan Check / Job No.
B20VN16032
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED REC ROOM WITH HALF BATHROOM
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 SELLA BENYAMIN
Corrections Issued 12/28/2020 SELLA BENYAMIN
Quality Review Completed 12/28/2020 STEVEN KIM
Building Plans Picked Up 1/8/2021 APPLICANT
Plan Check Approved 6/11/2021 SELLA BENYAMIN
Issued 6/25/2021 APPLICANT
CofO in Progress 7/29/2022 CHRISTOPHE COCHRAN
Permit Finaled 8/5/2022 RONALD MYRICK
CofO Issued 8/5/2022 RONALD MYRICK
Permit Finaled 8/5/2022 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/27/2021 LEE GUILBEAUX
ZI Cleared 3/23/2021 LAUREN PADICK
Construction near power lines Cleared 4/5/2021 RIDWAN HARDY
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/17/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/7/2021 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/14/2021 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 9/16/2021 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 9/20/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/13/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/16/2021 Approved ARAM AVEDISIAN
Green Building Rough 12/16/2021 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 12/16/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 12/16/2021 Approved ARAM AVEDISIAN
Shower Pan 12/20/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 1/28/2022 Partial Approval ARAM AVEDISIAN
Insulation 2/3/2022 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 2/14/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/15/2022 Approved CHRISTOPHE COCHRAN
Final 7/15/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 7/15/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/15/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 7/15/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 7/15/2022 Approved CHRISTOPHE COCHRAN
Final 7/29/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 7/29/2022 Approved CHRISTOPHE COCHRAN