4248 N RHODES AVE 91604
Certificate Information: 4248 N RHODES AVE 91604
- Application / Permit
- 20010-20000-04794
- Plan Check / Job No.
- B20VN16032
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 72'-4" X 37'-11" (2)-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/28/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Plan Check Approved | 6/11/2021 | SELLA BENYAMIN |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 7/29/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/2/2022 | RONALD MYRICK |
| CofO Issued | 8/2/2022 | RONALD MYRICK |
| Permit Finaled | 8/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Permit | Cleared | 1/26/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
| ZI | Cleared | 3/23/2021 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 3/30/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/7/2021 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2021 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/16/2021 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/20/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/10/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/13/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/16/2021 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/16/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 12/20/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/26/2022 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/28/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 2/3/2022 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/14/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/8/2022 | Approved | JOHN KIDWELL |
| Gas Test | 7/8/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 7/8/2022 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/15/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Gas Test | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/15/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 7/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/29/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/29/2022 | Approved | CHRISTOPHE COCHRAN |