5406 N FALLBROOK AVE 91367

Certificate Information: 5406 N FALLBROOK AVE 91367

Application / Permit
20010-20000-04787
Plan Check / Job No.
B20VN15996
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 21'5" ONE STORY DETACHED ACCESSORY DWELLINNG UNIT AS PER GCS 65852.2(E)(1)(B) and LAMC 12.22.A33(C)(D)(G), ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/9/2021
Issuing Office
Valley
Current Status
CofO Corrected on 7/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 RARES BODEA
Corrections Issued 12/19/2020 RARES BODEA
Quality Review Completed 12/24/2020 STEVEN KIM
Building Plans Picked Up 12/31/2020 APPLICANT
Applicant returned to address corrections 5/13/2021 RARES BODEA
Plan Check Approved 6/8/2021 RARES BODEA
Issued 6/9/2021 APPLICANT
CofO in Progress 6/14/2023 TROY SANDERS
Re-Activate Permit 7/5/2023 JOHN JANSON
CofO Issued-Status Void 7/5/2023 JOHN JANSON
Permit Finaled-Status Void 7/5/2023 JOHN JANSON
Permit Finaled 7/5/2023 JOHN JANSON
CofO Corrected 7/5/2023 JOHN JANSON
Permit Finaled 7/5/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG
Low Impact Development Cleared 3/16/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 3/17/2021 ABDULLAH SADOZAI
Construction near power lines Cleared 4/2/2021 RIDWAN HARDY
Construction within easement Cleared 4/2/2021 RIDWAN HARDY
GPI Written Notices Cleared 6/1/2021 RARES BODEA
Grading Pre-Inspection Cleared 6/1/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/14/2021 Partial Approval TROY SANDERS
Underground Mechanical 7/14/2021 Not Ready for Inspection TROY SANDERS
Excavation/Setback/Form/Re-Bar 9/17/2021 Approved TROY SANDERS
Footing/Foundation/Slab 9/17/2021 Approved TROY SANDERS
Underground Mechanical 9/17/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 2/17/2022 Partial Approval TROY SANDERS
HVAC-Rough 3/15/2022 Approved TROY SANDERS
PLUMBING-Rough 4/11/2022 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 4/15/2022 Approved DAVID SCANTLIN
HVAC-Rough 4/15/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 4/15/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/6/2022 Approved TROY SANDERS
Green Building Rough 5/6/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 5/6/2022 Approved TROY SANDERS
Drywall Nailing 6/15/2022 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 6/15/2022 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 8/10/2022 Approved TROY SANDERS
Interior/Exterior Lathing 8/10/2022 Partial Approval TROY SANDERS
ELECTRICAL-Final 10/24/2022 Partial Approval TROY SANDERS
Service/Power Release 10/24/2022 Not Required TROY SANDERS
Gas Test 2/24/2023 Approved TROY SANDERS
HVAC-Final 2/24/2023 Approved TROY SANDERS
Gas Test 2/27/2023 Approved TROY SANDERS
ELECTRICAL-Final 3/15/2023 Approved TROY SANDERS
PLUMBING-Final 3/15/2023 Approved TROY SANDERS
Final 6/13/2023 OK to Issue CofO TROY SANDERS
Green Building Final 6/13/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 6/13/2023 Approved TROY SANDERS