5408 N FALLBROOK AVE 91367
Certificate Information: 5408 N FALLBROOK AVE 91367
- Application / Permit
- 20010-20000-04786
- Plan Check / Job No.
- B20VN15996
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 59'6"X 35'6" 2-STORY SFD WITH ATTACHED GARAGE AND WITH 19'9" X 5' OPEN TRELLIS , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | RARES BODEA |
| Corrections Issued | 12/19/2020 | RARES BODEA |
| Quality Review Completed | 12/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/31/2020 | APPLICANT |
| Applicant returned to address corrections | 5/13/2021 | RARES BODEA |
| Plan Check Approved | 6/1/2021 | RARES BODEA |
| Issued | 6/9/2021 | APPLICANT |
| CofO in Progress | 6/22/2023 | TROY SANDERS |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
| CofO Issued | 6/30/2023 | JOHN JANSON |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 1/14/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/16/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/16/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 3/17/2021 | ABDULLAH SADOZAI |
| Trees in Parkway | Cleared | 4/14/2021 | JOHN KIM |
| GPI Written Notices | Cleared | 6/1/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 6/1/2021 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/6/2021 | Approved | TROY SANDERS |
| Sewer | 7/13/2021 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 7/13/2021 | Corrections Issued | TROY SANDERS |
| Sewer | 7/14/2021 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 7/14/2021 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 8/5/2021 | Corrections Issued | TROY SANDERS |
| PLUMBING-Rough | 9/3/2021 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/17/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 9/17/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Not Ready | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 2/17/2022 | Partial Approval | TROY SANDERS |
| HVAC-Rough | 3/15/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/11/2022 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 4/15/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 4/15/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 4/15/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/6/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 5/6/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 6/15/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 6/15/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Shower Pan | 8/3/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/10/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 10/24/2022 | Partial Approval | TROY SANDERS |
| Service/Power Release | 10/24/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 2/14/2023 | Not Ready for Inspection | TROY SANDERS |
| Pre-Inspection | 2/14/2023 | Approved | TROY SANDERS |
| Gas Test | 2/24/2023 | Approved | TROY SANDERS |
| HVAC-Final | 2/24/2023 | Approved | TROY SANDERS |
| Gas Test | 2/27/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/14/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/14/2023 | Approved | TROY SANDERS |
| Final | 6/9/2023 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 6/9/2023 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 6/9/2023 | Approved | HORACE FULTZ |
| Final | 6/21/2023 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 6/21/2023 | Approved | TROY SANDERS |