11810 N TUDOR CT 91326
Certificate Information: 11810 N TUDOR CT 91326
- Application / Permit
- 20010-20000-04759
- Plan Check / Job No.
- B20VN15958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- STATE APPROVED TEMPORARY SALES TRAILER (60' X 24') W/ ATTACHED PATIO COVER (30' X 12') & PARKING LOT
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- Pending
Pre - Inspection only, not a permit for construction
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/19/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/19/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Plan Check Approved | 3/26/2021 | NILOOFAR MEHRAIN |
| Issued | 4/20/2021 | APPLICANT |
| Permit Finaled | 1/5/2024 | JEFFREY FULTON |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Public Works-Open Permits | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/4/2021 | AMMAR ELTAWIL |
| DAS Clearance | Cleared | 3/9/2021 | NILOOFAR MEHRAIN |
| DAS Clearance | Cleared | 3/9/2021 | NORLITO MEDRANO |
| Hydrant and Access approval | Cleared | 3/15/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 3/26/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 3/26/2021 | NILOOFAR MEHRAIN |
| "T" removal | Cleared | 4/8/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 4/8/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 4/8/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 4/8/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 4/8/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 4/8/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 4/8/2021 | DANG NGUYEN |
| ZA Case | Cleared | 4/8/2021 | DANG NGUYEN |
| ZA Case | Cleared | 4/8/2021 | DANG NGUYEN |
| ZI | Cleared | 4/8/2021 | DANG NGUYEN |
| Grading Preinspection | Cleared | 4/20/2021 | OMID HEDAYAT |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Wong,, Ramon Roman; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/22/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/26/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 4/26/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/3/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/5/2021 | Approved | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/20/2021 | Partial Approval | ROBERT DAVIS |
| Final | 8/12/2021 | Partial Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/12/2021 | SGSOV No Gas | DANNY RODRIGUEZ |
| Smoke Detectors | 8/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 8/17/2021 | Conditional Approval | JONATHAN QUACH |
| Smoke Detectors | 8/17/2021 | Approved | JONATHAN QUACH |
| Verify Sprinkler Sign Off | 8/17/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 8/17/2021 | Approved | JONATHAN QUACH |
| Final | 9/3/2021 | No Access for Inspection | DANIEL VARNUM |
| Special/Order Compliance | 2/9/2022 | No Access for Inspection | JEFFREY FULTON |
| Final | 1/5/2024 | Permit Finaled | JEFFREY FULTON |