20653 W BLUEBIRD CT 91326

Certificate Information: 20653 W BLUEBIRD CT 91326

Application / Permit
20010-20000-04755
Plan Check / Job No.
B20VN15954
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #651 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 8/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 NILOOFAR MEHRAIN
Corrections Issued 1/21/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/21/2021 CHON CHIO KUO
Building Plans Picked Up 1/22/2021 APPLICANT
Plan Check Approved 6/9/2021 NILOOFAR MEHRAIN
Issued 7/15/2021 APPLICANT
CofO in Progress 8/19/2022 HENRY KIM
CofO Issued 8/22/2022 MICHAEL SMITH
Permit Finaled 8/22/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 5/5/2021 DANG NGUYEN
Address approval Cleared 5/5/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/5/2021 LEE GUILBEAUX
Permit Cleared 5/5/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/5/2021 LEE GUILBEAUX
Sewer availability Cleared 5/5/2021 LEE GUILBEAUX
Specific Plan Cleared 5/5/2021 DANG NGUYEN
Tract Map conditions Cleared 5/5/2021 DANG NGUYEN
Tract Map conditions Cleared 5/5/2021 DANG NGUYEN
ZA Case Cleared 5/5/2021 DANG NGUYEN
ZA Case Cleared 5/5/2021 DANG NGUYEN
ZI Cleared 5/5/2021 DANG NGUYEN
Public Works-Highway Ded. Cleared 5/5/2021 LEE GUILBEAUX
Low Impact Development Cleared 5/20/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 5/21/2021 ROBERT DUFF
GPI Written Notices Cleared 6/9/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 6/9/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/10/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 9/28/2021 Corrections Issued SEAN WIRCH
Footing/Foundation/Slab 9/30/2021 Approved SEAN WIRCH
Deputy Reinf. Concrete 10/1/2021 Approved SEAN WIRCH
Deputy Pre-Stress Concrete 10/13/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval HENRY KIM
Sewer 11/17/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Corrections Issued SEAN WIRCH
ELECTRICAL-Rough 2/9/2022 Approved HENRY KIM
HVAC-Rough 2/9/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval HENRY KIM
PLUMBING-Rough 2/22/2022 Approved HENRY KIM
Interior/Exterior Lathing 2/25/2022 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 3/7/2022 Corrections Issued HENRY KIM
Green Building Rough 3/7/2022 Approved HENRY KIM
Interior/Exterior Lathing 3/7/2022 Partial Approval HENRY KIM
MERV13>=Rough 3/7/2022 Approved HENRY KIM
Verify Sprinkler Sign Off 3/7/2022 Approved HENRY KIM
BUILDING-Rough-Frame 3/15/2022 Approved HENRY KIM
Drywall Nailing 4/4/2022 Approved HENRY KIM
Interior/Exterior Lathing 4/18/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 4/21/2022 Approved HENRY KIM
Gas Test 5/4/2022 Approved HENRY KIM
Underground Mechanical 5/4/2022 Not Ready for Inspection HENRY KIM
Underground Mechanical 5/6/2022 Approved HENRY KIM
Service/Power Release 5/31/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Not Ready HENRY KIM
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Approved HENRY KIM
ELECTRICAL-Final 8/19/2022 Approved HENRY KIM
Final 8/19/2022 OK to Issue CofO HENRY KIM
Green Building Final 8/19/2022 Approved HENRY KIM
HVAC-Final 8/19/2022 Approved HENRY KIM
MERV13>=Final 8/19/2022 Approved HENRY KIM
PLUMBING-Final 8/19/2022 Approved HENRY KIM
Smoke Detectors 8/19/2022 Approved HENRY KIM