20702 W BLUEBIRD CT 91326

Certificate Information: 20702 W BLUEBIRD CT 91326

Application / Permit
20010-20000-04752
Plan Check / Job No.
B20VN15954
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #651 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 NILOOFAR MEHRAIN
Corrections Issued 1/21/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/21/2021 CHON CHIO KUO
Building Plans Picked Up 1/22/2021 APPLICANT
Plan Check Approved 6/8/2021 NILOOFAR MEHRAIN
Issued 7/15/2021 APPLICANT
CofO in Progress 3/21/2023 HENRY KIM
No Progress 3/21/2023 HENRY KIM
CofO in Progress 3/22/2023 HENRY KIM
Permit Finaled 3/22/2023 MICHAEL SMITH
CofO Issued 3/22/2023 MICHAEL SMITH
Permit Finaled 3/22/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 5/5/2021 DANG NGUYEN
Address approval Cleared 5/5/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/5/2021 LEE GUILBEAUX
Permit Cleared 5/5/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/5/2021 LEE GUILBEAUX
Sewer availability Cleared 5/5/2021 LEE GUILBEAUX
Specific Plan Cleared 5/5/2021 DANG NGUYEN
Tract Map conditions Cleared 5/5/2021 DANG NGUYEN
Tract Map conditions Cleared 5/5/2021 DANG NGUYEN
ZA Case Cleared 5/5/2021 DANG NGUYEN
ZA Case Cleared 5/5/2021 DANG NGUYEN
ZI Cleared 5/5/2021 DANG NGUYEN
Public Works-Highway Ded. Cleared 5/5/2021 LEE GUILBEAUX
Low Impact Development Cleared 5/20/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 5/21/2021 ROBERT DUFF
GPI Written Notices Cleared 6/8/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 6/8/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2022 Partial Approval HENRY KIM
Sewer 6/6/2022 Approved HENRY KIM
Deputy Pre-Stress Concrete 6/22/2022 Approved HENRY KIM
Footing/Foundation/Slab 6/22/2022 Approved HENRY KIM
Deputy Reinf. Concrete 6/23/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Corrections Issued HENRY KIM
Deputy Wood Construction 9/6/2022 Conditional Approval HENRY KIM
PLUMBING-Rough 9/14/2022 Approved HENRY KIM
Deputy Wood Construction 9/20/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval HENRY KIM
ELECTRICAL-Rough 10/13/2022 Approved HENRY KIM
HVAC-Rough 10/13/2022 Approved HENRY KIM
BUILDING-Rough-Frame 10/19/2022 Approved HENRY KIM
Green Building Rough 10/19/2022 Approved HENRY KIM
Interior/Exterior Lathing 10/19/2022 Not Ready for Inspection HENRY KIM
Verify Sprinkler Sign Off 10/19/2022 Approved HENRY KIM
Interior/Exterior Lathing 10/24/2022 Partial Approval HENRY KIM
Insulation 11/4/2022 Approved HENRY KIM
Drywall Nailing 11/10/2022 Approved HENRY KIM
Interior/Exterior Lathing 11/10/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 11/15/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 11/17/2022 Approved HENRY KIM
Gas Test 1/20/2023 Approved HENRY KIM
Service/Power Release 1/20/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved HENRY KIM
Underground Mechanical 1/24/2023 Not Ready for Inspection HENRY KIM
Underground Mechanical 1/25/2023 Approved HENRY KIM
ELECTRICAL-Final 2/3/2023 Approved HENRY KIM
HVAC-Final 3/7/2023 Approved HENRY KIM
PLUMBING-Final 3/7/2023 Approved HENRY KIM
ELECTRICAL-Final 3/14/2023 Approved HENRY KIM
Final 3/14/2023 Corrections Issued HENRY KIM
Green Building Final 3/14/2023 Approved HENRY KIM
HVAC-Final 3/14/2023 Approved HENRY KIM
PLUMBING-Final 3/14/2023 Corrections Issued HENRY KIM
Smoke Detectors 3/14/2023 Approved HENRY KIM
Special/Order Compliance 3/14/2023 Partial Inspection MORRIS JACKSON
Final 3/20/2023 OK to Issue CofO HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved HENRY KIM
PLUMBING-Final 3/20/2023 Approved HENRY KIM