20726 W BLUEBIRD CT 91326

Certificate Information: 20726 W BLUEBIRD CT 91326

Application / Permit
20010-20000-04751
Plan Check / Job No.
B20VN15952
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #651 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 7/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 NILOOFAR MEHRAIN
Corrections Issued 1/21/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/21/2021 CHON CHIO KUO
Building Plans Picked Up 1/22/2021 APPLICANT
Applicant returned to address corrections 5/3/2021 NILOOFAR MEHRAIN
Plan Check Approved 5/13/2021 NILOOFAR MEHRAIN
Issued 5/24/2021 APPLICANT
CofO in Progress 7/19/2022 HENRY KIM
Permit Finaled 7/22/2022 MICHAEL SMITH
CofO Issued 7/22/2022 MICHAEL SMITH
Permit Finaled 7/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/15/2021 ROBERT DUFF
Address approval Cleared 4/13/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/13/2021 LEE GUILBEAUX
Permit Cleared 4/13/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/13/2021 LEE GUILBEAUX
Sewer availability Cleared 4/13/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/13/2021 LEE GUILBEAUX
"T" removal Cleared 4/14/2021 DANG NGUYEN
Low Impact Development Cleared 4/14/2021 AMMAR ELTAWIL
Specific Plan Cleared 4/14/2021 DANG NGUYEN
Tract Map conditions Cleared 4/14/2021 DANG NGUYEN
Tract Map conditions Cleared 4/14/2021 DANG NGUYEN
ZA Case Cleared 4/14/2021 DANG NGUYEN
ZA Case Cleared 4/14/2021 DANG NGUYEN
ZI Cleared 4/14/2021 DANG NGUYEN
GPI Written Notices Cleared 5/12/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 5/12/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/14/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 8/3/2021 Approved JOSEPH SAGEN
Deputy Reinf. Concrete 8/9/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Not Ready for Inspection JOSEPH SAGEN
Sewer 11/9/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval HENRY KIM
ELECTRICAL-Rough 1/18/2022 Approved HENRY KIM
HVAC-Rough 1/18/2022 Approved HENRY KIM
PLUMBING-Rough 2/1/2022 Approved HENRY KIM
BUILDING-Rough-Frame 2/8/2022 Approved HENRY KIM
Green Building Rough 2/8/2022 Approved HENRY KIM
MERV13>=Rough 2/8/2022 Approved HENRY KIM
Verify Sprinkler Sign Off 2/8/2022 Approved HENRY KIM
Interior/Exterior Lathing 2/10/2022 Partial Approval HENRY KIM
Drywall Nailing 2/25/2022 Approved HENRY KIM
Interior/Exterior Lathing 3/30/2022 Approved HENRY KIM
Gas Test 3/31/2022 Approved HENRY KIM
Service/Power Release 4/14/2022 Not Ready for Inspection HENRY KIM
Service/Power Release 4/18/2022 Corrections Issued HENRY KIM
Service/Power Release 4/20/2022 Approved HENRY KIM
Underground Mechanical 4/20/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved HENRY KIM
ELECTRICAL-Final 7/8/2022 Corrections Issued HENRY KIM
PLUMBING-Final 7/8/2022 Corrections Issued HENRY KIM
ELECTRICAL-Final 7/12/2022 Approved HENRY KIM
HVAC-Final 7/12/2022 Approved HENRY KIM
PLUMBING-Final 7/12/2022 Approved HENRY KIM
ELECTRICAL-Final 7/19/2022 Approved HENRY KIM
Final 7/19/2022 OK to Issue CofO HENRY KIM
Green Building Final 7/19/2022 Approved HENRY KIM
MERV13>=Final 7/19/2022 Approved HENRY KIM
PLUMBING-Final 7/19/2022 Approved HENRY KIM
Smoke Detectors 7/19/2022 Approved HENRY KIM