417 N KENTER AVE 90049
Certificate Information: 417 N KENTER AVE 90049
- Application / Permit
- 20010-20000-04711
- Plan Check / Job No.
- B20VN15869
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 75' X 57' 2-STORY SFD WITH ATTACHED 2 CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | RARES BODEA |
| Corrections Issued | 12/12/2020 | RARES BODEA |
| Quality Review Completed | 12/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/21/2020 | APPLICANT |
| Applicant returned to address corrections | 3/17/2021 | RARES BODEA |
| Plan Check Approved | 5/25/2021 | RARES BODEA |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 8/27/2022 | JUAN VALENZUELA |
| Permit Finaled | 9/12/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2022 | DANIEL ORRANTE |
| CofO Issued | 9/12/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2020 | DENNIS BRAGIN |
| Permit | Cleared | 12/26/2020 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 1/4/2021 | DENNIS BRAGIN |
| Trees in Parkway | Cleared | 1/7/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 2/4/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 3/17/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 3/17/2021 | RARES BODEA |
| Low Impact Development | Cleared | 3/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/26/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 4/15/2021 | JENSON LEE |
| Drainage to Storm Drain | Cleared | 4/16/2021 | MAHELET GEBEYHU |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/22/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/7/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/17/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 9/27/2021 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 9/30/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 9/30/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/30/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 9/30/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 9/30/2021 | Approved | JUAN VALENZUELA |
| Insulation | 10/15/2021 | Approved | BOBBY KEY |
| Shower Pan | 10/15/2021 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 10/26/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/26/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 6/27/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 6/27/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 6/27/2022 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 6/29/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 8/22/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 8/22/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Service/Power Release | 8/22/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 8/22/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/26/2022 | Approved | JUAN VALENZUELA |
| Final | 8/26/2022 | OK to Issue CofO | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 8/26/2022 | Approved | JUAN VALENZUELA |