14282 W BERG ST 91342

Certificate Information: 14282 W BERG ST 91342

Application / Permit
20010-20000-04697
Plan Check / Job No.
B20VN15821
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY 30' X 40' IRREGULAR SHAPE ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE AND 10'X 20'-6" OPEN TRELLIS PER LAMC 12.22.A33.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 SERGIO MUNIZ
Corrections Issued 1/4/2021 SERGIO MUNIZ
Quality Review Completed 1/21/2021 OMID HEDAYAT
Plan Check Approved 5/12/2021 SERGIO MUNIZ
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/14/2021 APPLICANT
CofO in Progress 9/23/2022 ARAM AVEDISIAN
CofO Issued 10/12/2022 MICHAEL SMITH
Permit Finaled 10/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/1/2021 JOHN CONNEALLY
Address approval Cleared 3/3/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/4/2021 GABRIEL ROBLES
Sewer availability Cleared 3/4/2021 GABRIEL ROBLES
Low Impact Development Cleared 5/2/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/3/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John Marshall; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/19/2021 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 5/19/2021 Partial Inspection MISAEL ESPARZA
Sewer 5/19/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/25/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 5/25/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 7/30/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/30/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 7/30/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/30/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/30/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/30/2021 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/30/2021 Approved JENNIFER RABUCHIN
Sewer 8/12/2021 Approved JAVIER RAMOS JR
Shower Pan 8/12/2021 Not Ready for Inspection JAVIER RAMOS JR
Underground Mechanical 8/12/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/19/2021 Partial Approval ADAM ESCOTO
Shower Pan 8/19/2021 Approved ADAM ESCOTO
ELECTRICAL-Rough 8/31/2021 Approved MISAEL ESPARZA
Insulation 8/31/2021 Approved MISAEL ESPARZA
Drywall Nailing 9/14/2021 Approved ADAM ESCOTO
Green Building Rough 9/14/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 11/15/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/2/2022 Approved ARAM AVEDISIAN
Final 9/2/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 9/2/2022 Approved ARAM AVEDISIAN
Green Building Final 9/2/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/2/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/2/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/23/2022 Approved ARAM AVEDISIAN
Final 9/23/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 9/23/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 9/23/2022 Approved ARAM AVEDISIAN
Service/Power Release 9/23/2022 Approved ARAM AVEDISIAN