215 N KENTER AVE 90049

Certificate Information: 215 N KENTER AVE 90049

Application / Permit
20010-20000-04670
Plan Check / Job No.
B20VN15735
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED, 2-STORY SINGLE FAMILY DWELLING W/ATT GARAGE. FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/11/2021
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 COLIN LOREDO
Corrections Issued 12/17/2020 COLIN LOREDO
Quality Review Completed 12/18/2020 OMID HEDAYAT
Building Plans Picked Up 12/21/2020 APPLICANT
Applicant returned to address corrections 3/9/2021 COLIN LOREDO
Applicant returned to address corrections 3/18/2021 COLIN LOREDO
Applicant returned to address corrections 3/30/2021 COLIN LOREDO
Plan Check Approved 4/22/2021 COLIN LOREDO
Issued 5/11/2021 APPLICANT
CofO in Progress 6/29/2022 JOHN KIDWELL
CofO in Progress 6/29/2022 JOHN KIDWELL
CofO in Progress 7/8/2022 DANIEL ORRANTE
Permit Finaled 7/8/2022 DANIEL ORRANTE
CofO Issued 7/8/2022 DANIEL ORRANTE
Permit Finaled 7/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 1/20/2021 NIKTA MOUSAVI
Trees in Parkway Cleared 1/28/2021 JOHN KIM
Hydrant and Access approval Cleared 2/3/2021 JEREMY CARTER
Low Impact Development Cleared 3/4/2021 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 3/23/2021 NIKTA MOUSAVI
Disturb/Remove Protected Trees Cleared 4/12/2021 RONALD TULL
Drainage to Storm Drain Cleared 4/22/2021 JENSON LEE
Roof/Waste drainage to street Cleared 4/22/2021 NIKTA MOUSAVI
Sewer availability Cleared 4/22/2021 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/7/2021 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 6/10/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/18/2021 Conditional Approval JUAN VALENZUELA
FLOOD-Elevation Certificate 6/18/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 6/18/2021 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 9/17/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 9/27/2021 Approved JUAN VALENZUELA
HVAC-Rough 9/27/2021 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 9/30/2021 Approved JUAN VALENZUELA
FLOOD-Proofing Certificate 9/30/2021 Approved JUAN VALENZUELA
Green Building Rough 9/30/2021 Approved JUAN VALENZUELA
HVAC-Rough 9/30/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/30/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/30/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 9/30/2021 Approved JUAN VALENZUELA
Insulation 10/8/2021 Conditional Approval RYAN SALAZAR
Shower Pan 10/8/2021 Approved RYAN SALAZAR
Drywall Nailing 10/15/2021 Approved BOBBY KEY
Interior/Exterior Lathing 10/15/2021 Approved BOBBY KEY
ELECTRICAL-Final 5/17/2022 Approved JOHN KIDWELL
PLUMBING-Final 5/17/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Not Ready JUAN VALENZUELA
Final 5/25/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 5/25/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 5/25/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 5/25/2022 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 5/25/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Not Ready JUAN VALENZUELA
Final 6/22/2022 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 6/22/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 6/22/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 6/22/2022 Not Ready for Inspection JUAN VALENZUELA
Final 6/27/2022 Conditional Approval JOHN KIDWELL
Footing/Foundation/Slab 6/27/2022 Approved JOHN KIDWELL
Service/Power Release 6/27/2022 Approved JOHN KIDWELL