4450 W MELBOURNE AVE 90027

Certificate Information: 4450 W MELBOURNE AVE 90027

Application / Permit
20010-20000-04619
Plan Check / Job No.
B20VN15593
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 29' DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 JEROME MAGAT PALMA
Corrections Issued 1/5/2021 JEROME MAGAT PALMA
Quality Review Completed 1/22/2021 OMID HEDAYAT
Plan Check Approved 4/15/2021 JEROME MAGAT PALMA
Issued 5/24/2021 APPLICANT
Building Plans Picked Up 5/26/2021 APPLICANT
CofO in Progress 7/13/2022 ALIZAH MAYAGOITIA
Permit Finaled 8/3/2022 DEROLD HAUFF
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/20/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 2/4/2021 CECILIO NAVARRO
Sewer availability Cleared 2/4/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 2/10/2021 BRIAN MILLER
Hydrant and Access approval Cleared 2/26/2021 KURT CORRAL
Construction near power lines Cleared 3/1/2021 RIDWAN HARDY
Low Impact Development Cleared 4/8/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/9/2021 ROSA SILVA
GPI Written Notices Cleared 4/15/2021 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2021 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/21/2021 Conditional Approval JOSEPH MCGARRY
Pre-Inspection 6/21/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/9/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/9/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/9/2021 Partial Approval JOSEPH MCGARRY
Sewer 7/9/2021 Approved JOSEPH MCGARRY
Underground Mechanical 7/9/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
ELECTRICAL-Rough 10/12/2021 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/12/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/12/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 10/28/2021 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 10/28/2021 Partial Approval JOSEPH MCGARRY
Green Building Rough 10/28/2021 Approved JOSEPH MCGARRY
HVAC-Rough 10/28/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 10/28/2021 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 10/28/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 10/28/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/9/2021 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/9/2021 Partial Approval JOSEPH MCGARRY
HVAC-Rough 11/9/2021 Approved JOSEPH MCGARRY
Insulation 11/18/2021 Corrections Issued JOSEPH MCGARRY
Insulation 11/23/2021 Approved JOSEPH MCGARRY
Drywall Nailing 12/3/2021 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 6/22/2022 Approved JOSEPH MCGARRY
Final 6/22/2022 Corrections Issued JOSEPH MCGARRY
Gas Test 6/22/2022 Approved JOSEPH MCGARRY
Green Building Final 6/22/2022 Approved JOSEPH MCGARRY
HVAC-Final 6/22/2022 Approved JOSEPH MCGARRY
PLUMBING-Final 6/22/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 6/22/2022 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 6/22/2022 Approved JOSEPH MCGARRY
Final 7/13/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 7/13/2022 Approved ALIZAH MAYAGOITIA