14042 W BESSEMER ST 91401
Certificate Information: 14042 W BESSEMER ST 91401
- Application / Permit
- 20010-20000-04618
- Plan Check / Job No.
- B20VN15576
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42' X 27'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/8/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/10/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/10/2020 | APPLICANT |
| Plan Check Approved | 3/2/2021 | SELLA BENYAMIN |
| Issued | 3/2/2021 | APPLICANT |
| CofO in Progress | 10/11/2022 | RICHARD DOCKUS |
| Permit Finaled | 10/12/2022 | DANIEL ORRANTE |
| CofO Issued | 10/12/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/21/2020 | LAUREN PADICK |
| Address approval | Cleared | 12/28/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/17/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Dream Remodeling Inc; Lic. No.: 889254-B | 22704 VENTURA BLVD #444 WOODLAND HILLS, CA 91411 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2021 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 5/14/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/16/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 8/16/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 8/16/2021 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 8/18/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 8/18/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 8/27/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/23/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 9/23/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/23/2021 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 9/23/2021 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 9/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 9/24/2021 | Approved | RICHARD DOCKUS |
| Insulation | 9/28/2021 | Conditional Approval | AMY COLIN |
| Drywall Nailing | 10/6/2021 | Approved | RICHARD DOCKUS |
| Shower Pan | 10/21/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 10/22/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 3/9/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 3/9/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 3/9/2022 | Not Required | RICHARD DOCKUS |
| Smoke Detectors | 3/9/2022 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 3/9/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 3/14/2022 | Approved | KRISTEN CAUSEY |
| Final | 3/21/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 9/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 10/6/2022 | OK to Issue CofO | RICHARD DOCKUS |