8722 N HAZELTINE AVE 91402
Certificate Information: 8722 N HAZELTINE AVE 91402
- Application / Permit
- 20010-20000-04607
- Plan Check / Job No.
- B20VN15557
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED IRREGULAR SHAPED, (23'-6" X 30'-5", 433 SQ. FT.) ACCESSORY DWELLING UNIT PER PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | COLIN LOREDO |
| Corrections Issued | 1/5/2021 | COLIN LOREDO |
| Quality Review Completed | 1/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Applicant returned to address corrections | 3/17/2021 | COLIN LOREDO |
| Plan Check Approved | 8/5/2021 | COLIN LOREDO |
| Issued | 9/16/2021 | APPLICANT |
| CofO in Progress | 8/31/2023 | GREGG CUMMINGS |
| No Progress | 9/1/2023 | GREGG CUMMINGS |
| CofO in Progress | 9/1/2023 | GREGG CUMMINGS |
| CofO in Progress | 4/30/2025 | VINCENT HANLEY |
| Permit Finaled | 5/8/2025 | RUBEN SALAS |
| CofO Issued | 5/8/2025 | RUBEN SALAS |
| Permit Finaled | 5/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/17/2021 | ADRIAN CASTRO |
| Construction within easement | Cleared | 7/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Ljm Remodel And Construction; Lic. No.: 1036730-B | 1114 EDANRUTH AVE LA PUENTE, CA 91746 |
| Engineer | Santos,, Michael Fernandez; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/6/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/18/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 3/24/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/26/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/26/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 4/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 4/26/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 4/26/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/24/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/24/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/24/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/9/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | GREGG CUMMINGS |
| Insulation | 7/5/2022 | Approved | WILLIAM WREN |
| Sewer | 7/5/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 8/10/2022 | Approved | WILLIAM WREN |
| HVAC-Final | 2/3/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/3/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/20/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 4/20/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 4/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 4/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/3/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/3/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/30/2023 | Approved | GREGG CUMMINGS |
| Final | 8/30/2023 | Conditional Approval | GREGG CUMMINGS |
| HVAC-Final | 8/30/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/30/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 8/30/2023 | Approved | GREGG CUMMINGS |
| Final | 9/1/2023 | Corrections Issued | GREGG CUMMINGS |
| Final | 4/30/2025 | OK to Issue CofO | VINCENT HANLEY |