11009 N SHARP AVE 91345

Certificate Information: 11009 N SHARP AVE 91345

Application / Permit
20010-20000-04547
Plan Check / Job No.
B20VN15371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27' X 44'-5" DETACHED ACCESSORY DWELLIGN UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 8/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 RAPHAEL ROSAS
Corrections Issued 12/15/2020 RAPHAEL ROSAS
Applicant returned to address corrections 5/1/2022 RAPHAEL ROSAS
Building Plans Picked Up 5/2/2022 APPLICANT
Plan Check Approved 8/9/2024 YAQUB MIRZA
Issued 8/23/2024 APPLICANT
CofO in Progress 2/11/2026 JOSE AVILA
Permit Finaled 2/17/2026 RUBEN SALAS
CofO Issued 2/17/2026 RUBEN SALAS
Permit Finaled 2/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/18/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/18/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/30/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 7/25/2024 KURT CORRAL
Low Impact Development Cleared 7/30/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/8/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 9/26/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 10/16/2024 Partial Approval JENNIFER RABUCHIN
Deputy Reinf. Concrete 10/22/2024 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/22/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 10/22/2024 Approved JENNIFER RABUCHIN
METHANE-Barrier 10/22/2024 Approved JENNIFER RABUCHIN
METHANE-Subgrade 10/22/2024 Approved JENNIFER RABUCHIN
Gas Test 11/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
Sewer 11/7/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 11/7/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/6/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/6/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/6/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 2/6/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/6/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/21/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/21/2025 Approved JENNIFER RABUCHIN
Green Building Rough 2/21/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 2/21/2025 Approved JENNIFER RABUCHIN
MERV13>=Rough 2/21/2025 Approved JENNIFER RABUCHIN
METHANE-Barrier 2/21/2025 Approved JENNIFER RABUCHIN
METHANE-Rough 2/21/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/21/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 2/21/2025 Approved JENNIFER RABUCHIN
Insulation 3/5/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 3/11/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 4/23/2025 Not Ready for Inspection RAUL OLAGI
Shower Pan 4/23/2025 Approved RAUL OLAGI
Special/Order Compliance 4/23/2025 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 4/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 4/25/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/19/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 5/19/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/25/2025 Approved JENNIFER RABUCHIN
Final 11/25/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/25/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 11/25/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/25/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 11/25/2025 Approved JENNIFER RABUCHIN
Final 1/29/2026 OK to Issue CofO JENNIFER RABUCHIN