20643 W DEER GRASS CT 91326
Certificate Information: 20643 W DEER GRASS CT 91326
- Application / Permit
- 20010-20000-04489
- Plan Check / Job No.
- B20VN15211
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN 651_PLAN 2D_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | DAWN MC NULTY |
| Corrections Issued | 12/30/2020 | DAWN MC NULTY |
| Quality Review Completed | 12/30/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/5/2021 | APPLICANT |
| Plan Check Approved | 7/18/2021 | DAWN MC NULTY |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | HENRY KIM |
| CofO Issued | 10/6/2022 | MICHAEL SMITH |
| Permit Finaled | 10/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/15/2021 | ROBERT DUFF |
| "T" removal | Cleared | 6/2/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 6/2/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/2/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/2/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/2/2021 | DANG NGUYEN |
| Address approval | Cleared | 6/3/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | LEE GUILBEAUX |
| Permit | Cleared | 6/3/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/3/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/3/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/3/2021 | LEE GUILBEAUX |
| CPC | Cleared | 6/9/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 6/28/2021 | AMMAR ELTAWIL |
Contact Information
| Architect | Swift,, Daniel R; Lic. No.: C32860 | 4601 WESTOWN PARKWAY SUITE 208 WEST DES MOINES, IA 50266 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 26772 DESERT LOCUST ST MURRIETA, CA 92562 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/23/2021 | Approved | SEAN WIRCH |
| Underground Mechanical | 12/23/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 2/4/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 4/12/2022 | Approved | SEAN WIRCH |
| Deputy Wood Construction | 5/2/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 5/13/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 5/19/2022 | Approved | HENRY KIM |
| HVAC-Rough | 5/19/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/19/2022 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | HENRY KIM |
| Green Building Rough | 5/23/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/23/2022 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 5/23/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/25/2022 | Partial Approval | HENRY KIM |
| Insulation | 6/6/2022 | Corrections Issued | HENRY KIM |
| Insulation | 6/9/2022 | Approved | HENRY KIM |
| Drywall Nailing | 6/16/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/6/2022 | Approved | HENRY KIM |
| Special/Order Compliance | 7/6/2022 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 7/27/2022 | Approved | HENRY KIM |
| Gas Test | 8/22/2022 | Approved | JEFFREY PARD |
| Service/Power Release | 8/22/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | HENRY KIM |
| ELECTRICAL-Final | 9/26/2022 | Corrections Issued | HENRY KIM |
| HVAC-Final | 9/26/2022 | Approved | HENRY KIM |
| PLUMBING-Final | 9/26/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/29/2022 | Approved | HENRY KIM |
| Final | 9/29/2022 | Corrections Issued | HENRY KIM |
| Green Building Final | 9/29/2022 | Approved | HENRY KIM |
| Smoke Detectors | 9/29/2022 | Approved | HENRY KIM |
| Final | 9/30/2022 | OK to Issue CofO | HENRY KIM |