11566 W LA MAIDA ST 91601
Certificate Information: 11566 W LA MAIDA ST 91601
- Application / Permit
- 20010-20000-04481
- Plan Check / Job No.
- B20VN15203
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 48' X 53'-5" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | SELLA BENYAMIN |
| Corrections Issued | 1/7/2021 | SELLA BENYAMIN |
| Quality Review Completed | 1/7/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Plan Check Approved | 5/21/2021 | SELLA BENYAMIN |
| Issued | 5/21/2021 | APPLICANT |
| CofO in Progress | 4/5/2022 | MICHAEL SMITH |
| Permit Finaled | 4/7/2022 | MICHAEL SMITH |
| CofO Issued | 4/7/2022 | MICHAEL SMITH |
| Permit Finaled | 4/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/3/2021 | KURT CORRAL |
| Trees in Parkway | Cleared | 3/8/2021 | JOHN KIM |
| Specific Plan | Cleared | 3/17/2021 | ERIN NASH |
| Low Impact Development | Cleared | 5/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/12/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/10/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 6/17/2021 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/18/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 6/18/2021 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/23/2021 | Approved | THOMAS FINNILA |
| Underground Mechanical | 6/23/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 6/28/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 6/30/2021 | Conditional Approval | ALAN MORELOS |
| HVAC-Rough | 7/20/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 7/20/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/22/2021 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Partial Approval | THOMAS FINNILA |
| Pre-Inspection | 8/3/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/5/2021 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/6/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 8/6/2021 | Approved | THOMAS FINNILA |
| Insulation | 8/10/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/12/2021 | Approved | THOMAS FINNILA |
| Shower Pan | 8/12/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 8/18/2021 | Approved | LILIANA PORTILLO |
| HVAC-Final | 12/23/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 12/28/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 12/30/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 12/30/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 1/3/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 3/17/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 3/17/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 3/17/2022 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 3/17/2022 | Approved | DAVID MATSON |
| Verify Rec and Parks Fee Memo | 3/17/2022 | Approved | DAVID MATSON |
| Final | 3/22/2022 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 3/22/2022 | Approved | DAVID MATSON |