10918 W NETTLETON ST 91352

Certificate Information: 10918 W NETTLETON ST 91352

Application / Permit
20010-20000-04455
Plan Check / Job No.
B20VN15084
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40' X 25' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/13/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 SELLA BENYAMIN
Corrections Issued 12/3/2020 SELLA BENYAMIN
Building Plans Picked Up 12/10/2020 APPLICANT
Plan Check Approved 7/9/2021 SELLA BENYAMIN
Issued 8/13/2021 APPLICANT
CofO in Progress 10/8/2022 DAVID ANDERSON
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/22/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/28/2020 LEE GUILBEAUX
Sewer availability Cleared 12/28/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/28/2020 LEE GUILBEAUX
ZA Case Cleared 12/31/2020 LAUREN PADICK
ZA Case Cleared 12/31/2020 LAUREN PADICK
Hydrant and Access approval Cleared 3/19/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/28/2021 TA ANH
Roof/Waste drainage to street Cleared 7/26/2021 CARLOS AGUILERA

Contact Information

Contractor Maya Construction; Lic. No.: 897113-B 11101 DE GARMO AVE      PACOIMA, CA 91331

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2021 Approved WILLIAM KUEHN
Footing/Foundation/Slab 9/9/2021 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 9/21/2021 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 9/21/2021 Partial Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 9/21/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 10/19/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 10/19/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 10/19/2021 Not Ready for Inspection WILLIAM KUEHN
HVAC-Rough 10/19/2021 Approved WILLIAM KUEHN
MERV13>=Rough 10/19/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 10/19/2021 Approved WILLIAM KUEHN
Shower Pan 10/19/2021 Approved WILLIAM KUEHN
Insulation 11/3/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 11/3/2021 Approved WILLIAM KUEHN
Drywall Nailing 11/9/2021 Approved WILLIAM KUEHN
ELECTRICAL-Final 2/8/2022 Corrections Issued MATTHEW NELSON
HVAC-Final 2/8/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Final 2/8/2022 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 3/16/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/16/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 3/16/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 3/16/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 3/16/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 3/16/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 9/14/2022 Corrections Issued DAVID ANDERSON
Green Building Final 9/14/2022 Approved DAVID ANDERSON
HVAC-Final 9/14/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Final 9/14/2022 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved DAVID ANDERSON
ELECTRICAL-Final 10/7/2022 Approved DAVID ANDERSON
Final 10/7/2022 OK to Issue CofO DAVID ANDERSON
HVAC-Final 10/7/2022 Approved DAVID ANDERSON
MERV13>=Final 10/7/2022 Approved DAVID ANDERSON
PLUMBING-Final 10/7/2022 Approved DAVID ANDERSON
Service/Power Release 10/7/2022 Approved DAVID ANDERSON