22039 W VANOWEN ST 91303
Certificate Information: 22039 W VANOWEN ST 91303
- Application / Permit
- 20010-20000-04451
- Plan Check / Job No.
- B20VN15063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' X 30' DETACHED TWO STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 12/22/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 12/22/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/30/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 4/7/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/8/2021 | JEROME MAGAT PALMA |
| Issued | 4/9/2021 | APPLICANT |
| Building Plans Picked Up | 4/12/2021 | APPLICANT |
| CofO in Progress | 6/9/2022 | TROY SANDERS |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
| CofO Issued | 6/15/2022 | JOHN JANSON |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 12/31/2020 | LAUREN PADICK |
| Address approval | Cleared | 1/5/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 2/4/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/17/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/18/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2021 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 6/30/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/19/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 8/19/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/23/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 8/23/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 8/23/2021 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 8/24/2021 | Partial Approval | TROY SANDERS |
| Deputy Wood Construction | 8/24/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/25/2021 | Partial Inspection | STEPHANIE SWANSON |
| Shower Pan | 8/25/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/31/2021 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 9/3/2021 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 9/15/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/15/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 9/23/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/30/2021 | Approved | TROY SANDERS |
| Service/Power Release | 1/14/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | TROY SANDERS |
| Final | 5/6/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 5/6/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/6/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/6/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 5/6/2022 | Approved | TROY SANDERS |
| Final | 6/9/2022 | OK to Issue CofO | TROY SANDERS |