14613 S DENVER AVE 90248

Certificate Information: 14613 S DENVER AVE 90248

Application / Permit
20010-20000-04397
Plan Check / Job No.
B20VN14968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 13' X 35' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (E) WITH 6' X 13' FRONT PORCH, ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 RARES BODEA
Corrections Issued 12/1/2020 RARES BODEA
Building Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 5/22/2021 RARES BODEA
Plan Check Approved 6/7/2021 RARES BODEA
Issued 6/7/2021 APPLICANT
CofO in Progress 3/16/2022 JOHN KLARIN
Permit Finaled 3/16/2022 DEROLD HAUFF
CofO Issued 3/16/2022 DEROLD HAUFF
Permit Finaled 3/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/18/2021 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 3/2/2021 YEGANEH SADEGHI
Sewer availability Cleared 3/4/2021 YEGANEH SADEGHI
Low Impact Development Cleared 3/29/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/30/2021 CHINH DINH
Construction near power lines Cleared 5/6/2021 RIDWAN HARDY
Construction within easement Cleared 5/6/2021 RIDWAN HARDY

Contact Information

Architect Jones,, Michael Sterling; Lic. No.: C24740 510 MARGUERITA AVENUE      SANTA MONICA, CA 90402
Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/7/2021 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 7/7/2021 Approved EUGENE CASSIDY
METHANE-Subgrade 7/7/2021 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/20/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 7/20/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/16/2021 Conditional Approval EUGENE CASSIDY
Green Building Rough 8/16/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 8/16/2021 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/16/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 8/16/2021 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 8/16/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/18/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 8/18/2021 Not Ready for Inspection EUGENE CASSIDY
Insulation 8/18/2021 Partial Approval EUGENE CASSIDY
MERV13>=Rough 8/18/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 8/18/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Approved JOHN KLARIN
Wood Frame 9/2/2021 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Approved EUGENE CASSIDY
Insulation 9/7/2021 Approved EUGENE CASSIDY
Shower Pan 9/7/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/13/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 9/13/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 9/13/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 9/13/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 9/13/2021 Corrections Issued EUGENE CASSIDY
Shower Pan 9/13/2021 Approved EUGENE CASSIDY
Insulation 9/21/2021 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 9/21/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/21/2021 Approved EUGENE CASSIDY
Sewer 9/21/2021 Approved EUGENE CASSIDY
Underground Mechanical 9/21/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/28/2021 Conditional Approval EUGENE CASSIDY
Green Building Rough 9/28/2021 Approved EUGENE CASSIDY
Insulation 9/28/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/28/2021 Approved EUGENE CASSIDY
Drywall Nailing 10/2/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/2/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/3/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/29/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/29/2021 Not Ready for Inspection EUGENE CASSIDY
Final 11/29/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 11/29/2021 Approved EUGENE CASSIDY
HVAC-Final 11/29/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 11/29/2021 Approved EUGENE CASSIDY
PLUMBING-Final 11/29/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 11/29/2021 Not Required EUGENE CASSIDY
Smoke Detectors 11/29/2021 Approved EUGENE CASSIDY
Final 2/11/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved JOHN KLARIN
Final 3/3/2022 Not Ready for Inspection JOHN KLARIN
Final 3/11/2022 Not Ready for Inspection JOHN KLARIN
Final 3/15/2022 OK to Issue CofO JOHN KLARIN