Excavation/Setback/Form/Re-Bar
|
3/15/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
3/23/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
3/31/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
4/1/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/5/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/7/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/8/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/8/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
4/8/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/8/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/13/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
4/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
4/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/13/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/14/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/17/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/18/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
5/18/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
5/18/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
5/18/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/20/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
6/3/2022
|
Approved
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
6/6/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
6/6/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
6/15/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
6/30/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
7/18/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/18/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
8/2/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
8/3/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
8/4/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
8/5/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
8/15/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
8/15/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/17/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
8/17/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
8/17/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
8/19/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
8/24/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/24/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
8/24/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
8/24/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
8/26/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/16/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/23/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Wood Frame
|
9/23/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
9/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
10/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
10/12/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
10/12/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/26/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
10/26/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/16/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
11/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
11/29/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
12/2/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
12/2/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/19/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
12/28/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
5/3/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
5/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
5/12/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Drywall Nailing
|
6/29/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
8/24/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
9/28/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
9/28/2023
|
SGSOV Not Ready
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Wood Frame
|
9/28/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
10/23/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/23/2023
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
10/24/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Final
|
10/25/2023
|
OK to Issue CofO
|
EDWIN GREGORYONA
|