14738 W LEADWELL ST 91405

Certificate Information: 14738 W LEADWELL ST 91405

Application / Permit
20010-20000-04395
Plan Check / Job No.
B20VN14966
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1,200 SQ. FT. ACCESSORY DWELLING UNIT. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 SELLA BENYAMIN
Corrections Issued 11/30/2020 SELLA BENYAMIN
Applicant returned to address corrections 5/28/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 7/12/2022 JESSE ARELLANO
Applicant returned to address corrections 7/28/2022 JESSE ARELLANO
Building Plans Picked Up 8/2/2022 APPLICANT
Applicant returned to address corrections 8/23/2022 RACHEL BEYENE
Plan Check Approved 8/23/2022 RAHEL BEYENE
Issued 8/29/2022 APPLICANT
CofO in Progress 8/15/2023 MATTHEW NELSON
CofO Issued 11/6/2023 RUBEN SALAS
Permit Finaled 11/6/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/3/2021 CARLOS AGUILERA
Sewer availability Cleared 6/14/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/27/2021 MATTHEW CRAIG
Construction within easement Cleared 4/5/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 7/21/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/14/2022 Partial Approval GREGG CUMMINGS
Sewer 10/14/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/19/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/19/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 10/21/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 10/21/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/21/2022 Approved GREGG CUMMINGS
Green Building Rough 10/21/2022 Off-Hour Fees Due
Verify Sprinkler Sign Off 10/21/2022 Off-Hour Fees Due
Deputy Drilled-In Anchors 11/21/2022 Conditional Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval MATTHEW NELSON
HVAC-Rough 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Underground Mechanical 11/29/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/30/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/30/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 11/30/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 11/30/2022 Approved GREGG CUMMINGS
Shower Pan 11/30/2022 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 12/6/2022 Approved GREGG CUMMINGS
Green Building Rough 12/6/2022 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 12/6/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 12/6/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 12/15/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Green Building Rough 12/15/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 12/20/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/20/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 1/5/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/5/2023 Approved GREGG CUMMINGS
Final 5/18/2023 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 7/15/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 7/15/2023 Corrections Issued CHRIS CHRISTENSEN
Final 7/15/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/15/2023 Approved CHRIS CHRISTENSEN
HVAC-Final 7/15/2023 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 7/15/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/15/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 7/15/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 7/15/2023 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 7/15/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/31/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 7/31/2023 Not Ready for Inspection GREGG CUMMINGS
Final 7/31/2023 Corrections Issued GREGG CUMMINGS
HVAC-Final 7/31/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 7/31/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 7/31/2023 Not Ready for Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 7/31/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 8/7/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 8/7/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 8/7/2023 Not Ready for Inspection GREGG CUMMINGS
Final 8/11/2023 OK to Issue CofO MATTHEW NELSON
Service/Power Release 8/11/2023 Approved MATTHEW NELSON