5001 N HESPERIA AVE 91316

Certificate Information: 5001 N HESPERIA AVE 91316

Application / Permit
20010-20000-04394
Plan Check / Job No.
B20VN14959
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED 21' X 21' GARAGE
Permit Issued
Issued on 12/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 SELLA BENYAMIN
Corrections Issued 1/28/2021 SELLA BENYAMIN
Quality Review Completed 2/4/2021 STEVEN KIM
Building Plans Picked Up 2/11/2021 APPLICANT
Applicant returned to address corrections 10/6/2022 SELLA BENYAMIN
Plan Check Approved 10/13/2022 SELLA BENYAMIN
Issued 12/12/2022 APPLICANT
CofO in Progress 5/23/2024 JOHN KIDWELL
Permit Finaled 6/11/2024 JOHN JANSON
CofO Issued 6/11/2024 JOHN JANSON
Permit Finaled 6/11/2024 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 4/7/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 5/7/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 9/27/2021 GABRIEL ROBLES
Low Impact Development Cleared 2/2/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/13/2022 ABDULLAH SADOZAI
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA
GPI Written Notices Cleared 10/13/2022 SELLA BENYAMIN

Contact Information

Contractor True Source Design & Development Group Corp; Lic. No.: 911508-B 5151 CALATRANA DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2023 Approved DAVID SANDOVAL
Footing/Foundation/Slab 1/27/2023 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved DAVID SANDOVAL
Deputy Wood Construction 5/15/2023 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 5/9/2024 Approved JOHN KIDWELL
Final 5/9/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 5/9/2024 Approved JOHN KIDWELL
Green Building Rough 5/9/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved JOHN KIDWELL
Service/Power Release 5/9/2024 Approved JOHN KIDWELL
Smoke Detectors 5/9/2024 Approved JOHN KIDWELL
Final 5/22/2024 OK to Issue CofO JOHN KIDWELL