5001 N HESPERIA AVE 91316
Certificate Information: 5001 N HESPERIA AVE 91316
- Application / Permit
- 20010-20000-04394
- Plan Check / Job No.
- B20VN14959
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 21' X 21' GARAGE
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | SELLA BENYAMIN |
| Corrections Issued | 1/28/2021 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| Applicant returned to address corrections | 10/6/2022 | SELLA BENYAMIN |
| Plan Check Approved | 10/13/2022 | SELLA BENYAMIN |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | JOHN KIDWELL |
| Permit Finaled | 6/11/2024 | JOHN JANSON |
| CofO Issued | 6/11/2024 | JOHN JANSON |
| Permit Finaled | 6/11/2024 | JOHN JANSON |
Permit Application Clearance Information
| Permit | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 5/7/2021 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 2/2/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/13/2022 | ABDULLAH SADOZAI |
| Trees in Parkway | Cleared | 4/19/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 10/13/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | True Source Design & Development Group Corp; Lic. No.: 911508-B | 5151 CALATRANA DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/27/2023 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 5/15/2023 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | JOHN KIDWELL |
| Final | 5/9/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 5/9/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/9/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 5/9/2024 | Approved | JOHN KIDWELL |
| Smoke Detectors | 5/9/2024 | Approved | JOHN KIDWELL |
| Final | 5/22/2024 | OK to Issue CofO | JOHN KIDWELL |