10822 N MCLENNAN AVE 91344
Certificate Information: 10822 N MCLENNAN AVE 91344
- Application / Permit
- 20010-20000-04387
- Plan Check / Job No.
- B20VN14881
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (22'-0"x 31'-4") IRR SHAPE 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | TROY DEGUZMAN |
| Corrections Issued | 12/20/2020 | TROY DEGUZMAN |
| Quality Review Completed | 12/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Plan Check Approved | 11/29/2021 | TROY DEGUZMAN |
| Issued | 11/30/2021 | APPLICANT |
| CofO in Progress | 3/14/2023 | JAVIER RAMOS JR |
| Permit Finaled | 4/3/2023 | MICHAEL SMITH |
| CofO Issued | 4/3/2023 | MICHAEL SMITH |
| Permit Finaled | 4/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/25/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/22/2021 | MITESH PATEL |
| Construction near power lines | Cleared | 10/8/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/8/2021 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/10/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 11/29/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/18/2022 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 1/24/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/27/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2022 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/12/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/12/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 4/25/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/6/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 5/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/6/2022 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 5/16/2022 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/19/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/19/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 5/26/2022 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Sewer | 9/1/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/1/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/13/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Gas Test | 10/13/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/13/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 10/13/2022 | Approved | JAVIER RAMOS JR |
| Final | 1/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 1/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 1/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 1/30/2023 | Corrections Issued | JOHN COLEMAN |
| Final | 2/22/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 2/22/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 2/22/2023 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/22/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/14/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/14/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/14/2023 | Approved | JAVIER RAMOS JR |