6118 N ETHEL AVE 91401
Certificate Information: 6118 N ETHEL AVE 91401
- Application / Permit
- 20010-20000-04380
- Plan Check / Job No.
- B20VN14842
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW DETACHED 1-STORY 47' 9" X 40' IRR-SHAPED ACCESSORY LIVING QUARTERS. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/21/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 11/24/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/10/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/6/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/11/2021 | APPLICANT |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 12/23/2022 | JOHN COLEMAN |
| CofO Issued | 12/23/2022 | MICHAEL SMITH |
| Permit Finaled | 12/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/22/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 3/26/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Best Remodeling And Development; Lic. No.: 988425-B | 17609 VENTURA BLVD #LL08 ENCINO, CA 91316 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/30/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/25/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/25/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 10/25/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/27/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/3/2021 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 12/6/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/9/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 12/14/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/11/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 1/11/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 1/13/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 5/20/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 5/20/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 5/20/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 5/20/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 5/20/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/20/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/20/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 6/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 6/30/2022 | Corrections Issued | RAFAEL CORTES |
| Service/Power Release | 6/30/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/19/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 7/19/2022 | Approved | RAFAEL CORTES |
| Final | 8/3/2022 | Conditional Approval | RAFAEL CORTES |
| Service/Power Release | 8/3/2022 | Approved | RAFAEL CORTES |
| Final | 11/28/2022 | Corrections Issued | JOHN COLEMAN |