20632 W DEER GRASS CT 91326

Certificate Information: 20632 W DEER GRASS CT 91326

Application / Permit
20010-20000-04367
Plan Check / Job No.
B20VN14735
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN 649_PLAN 2BR_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 8/2/2021
Issuing Office
Current Status
CofO Issued on 10/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 DAWN MC NULTY
Corrections Issued 12/22/2020 DAWN MC NULTY
Quality Review Completed 12/23/2020 CHON CHIO KUO
Building Plans Picked Up 1/5/2021 APPLICANT
Applicant returned to address corrections 5/4/2021 DAWN MC NULTY
Plan Check Approved 7/27/2021 DAWN MC NULTY
Issued 8/2/2021 APPLICANT
CofO in Progress 10/14/2022 HENRY KIM
Permit Finaled 10/14/2022 MICHAEL SMITH
CofO Issued 10/14/2022 MICHAEL SMITH
Permit Finaled 10/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/21/2021 ROBERT DUFF
Address approval Cleared 6/3/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/3/2021 LEE GUILBEAUX
Permit Cleared 6/3/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/3/2021 LEE GUILBEAUX
Sewer availability Cleared 6/3/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/3/2021 LEE GUILBEAUX
"T" removal Cleared 6/15/2021 LAUREN PADICK
CPC Cleared 6/15/2021 LAUREN PADICK
Specific Plan Cleared 6/15/2021 LAUREN PADICK
Tract Map conditions Cleared 6/15/2021 LAUREN PADICK
ZA Case Cleared 6/15/2021 LAUREN PADICK
ZA Case Cleared 6/15/2021 LAUREN PADICK
Low Impact Development Cleared 6/28/2021 AMMAR ELTAWIL

Contact Information

Architect Niemerski, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Nelson, William Mc Kee; Lic. No.: S3417 5 DELLWOOD      DOVE CANYON, CA 92679
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/16/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 12/13/2021 Approved HENRY KIM
Deputy Reinf. Concrete 12/22/2021 Approved SEAN WIRCH
Sewer 1/11/2022 Approved SEAN WIRCH
Deputy Pre-Stress Concrete 1/12/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval SEAN WIRCH
Pre-Inspection 3/22/2022 Corrections Issued SEAN WIRCH
Underground Mechanical 4/1/2022 Approved SEAN WIRCH
Deputy Wood Construction 5/6/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 5/26/2022 Approved SEAN WIRCH
PLUMBING-Rough 5/26/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 6/14/2022 Approved SEAN WIRCH
Green Building Rough 6/14/2022 Approved SEAN WIRCH
HVAC-Rough 6/14/2022 Approved SEAN WIRCH
Verify Sprinkler Sign Off 6/14/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 6/16/2022 Partial Approval SEAN WIRCH
Drywall Nailing 6/29/2022 Not Ready for Inspection HENRY KIM
Drywall Nailing 7/1/2022 Not Ready for Inspection HENRY KIM
Drywall Nailing 7/6/2022 Approved SEAN WIRCH
Gas Test 8/23/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Approved HENRY KIM
Service/Power Release 9/9/2022 Approved HENRY KIM
ELECTRICAL-Final 10/11/2022 Approved HENRY KIM
HVAC-Final 10/11/2022 Corrections Issued HENRY KIM
PLUMBING-Final 10/11/2022 Corrections Issued HENRY KIM
Final 10/13/2022 OK to Issue CofO HENRY KIM
Green Building Final 10/13/2022 Approved HENRY KIM
HVAC-Final 10/13/2022 Approved HENRY KIM
PLUMBING-Final 10/13/2022 Approved HENRY KIM
Smoke Detectors 10/13/2022 Approved HENRY KIM