1352 E VIENNA WAY 90291
Certificate Information: 1352 E VIENNA WAY 90291
- Application / Permit
- 20010-20000-04351
- Plan Check / Job No.
- B20VN14772
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU WITH ROOF DECK OER LAMC 12.22.A.(c)&(d)
- Permit Issued
- Issued on 5/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | CHON CHIO KUO |
| Corrections Issued | 12/23/2020 | CHON CHIO KUO |
| Quality Review Completed | 12/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/31/2020 | APPLICANT |
| Applicant returned to address corrections | 4/22/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/27/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/3/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/11/2021 | CHON CHIO KUO |
| Plan Check Approved | 5/12/2021 | CHON CHIO KUO |
| Issued | 5/13/2021 | APPLICANT |
| CofO in Progress | 6/20/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
| CofO Issued | 7/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | DINAH GARIN |
| Permit | Cleared | 1/11/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/13/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/23/2021 | JOHN CONNEALLY |
| Specific Plan | Cleared | 3/23/2021 | FREDDY GARCIA |
| Low Impact Development | Cleared | 4/19/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/30/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/15/2021 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/24/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 7/7/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2021 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Not Ready for Inspection | PIERRE VEGA |
| Shower Pan | 8/4/2021 | Approved | PIERRE VEGA |
| Wood Frame | 8/4/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 8/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 8/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/5/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/9/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 8/9/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/12/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/1/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 9/2/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 9/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/5/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/5/2021 | Partial Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 10/5/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 10/6/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 10/15/2021 | Approved | DAVID FEILER |
| Gas Test | 2/4/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 2/25/2022 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 3/18/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 3/18/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 3/31/2022 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 3/31/2022 | Approved | CLAYTON GRAHAM |
| Final | 4/12/2022 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 4/12/2022 | Approved | DAVID FEILER |
| Green Building Final | 4/12/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 4/12/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 4/12/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 4/13/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 4/13/2022 | Approved | DAVID FEILER |
| Special/Order Compliance | 4/13/2022 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 4/13/2022 | Partial Inspection | MICHAEL PELHAM |
| Final | 5/13/2022 | Partial Inspection | DAVID FEILER |
| Service/Power Release | 5/13/2022 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Final | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Final | 6/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 6/17/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/17/2022 | Approved | JESUS RODRIGUEZ |