8612 N HANNA AVE 91304
Certificate Information: 8612 N HANNA AVE 91304
- Application / Permit
- 20010-20000-04349
- Plan Check / Job No.
- B20VN14769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT ( 26'-10"X19'-4") per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 12/16/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 12/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Plan Check Approved | 7/14/2021 | MOHAMMAD ESMAILI |
| Issued | 7/29/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 8/25/2022 | JOHN JANSON |
| Permit Finaled | 8/25/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/28/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | GABRIEL ROBLES |
| Hold | Cleared | 2/22/2021 | JASON SHEETS |
| Sewer availability | Cleared | 2/22/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/15/2021 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 7/14/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | I Team Builders And Design Inc; Lic. No.: 1029756-B | 22647 VENTURA BLVD #265 WOODLAND HILLS, CA 91364 |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/1/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/22/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 11/22/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 11/22/2021 | Approved | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 11/22/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 11/30/2021 | Corrections Issued | PETER FOLLING |
| Shower Pan | 11/30/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | JUSTIN HAWLEY |
| HVAC-Rough | 12/6/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 12/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Sewer | 12/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 12/8/2021 | Approved | JESUS PINEDA |
| Insulation | 12/8/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/8/2021 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 12/9/2021 | Partial Approval | JESUS PINEDA |
| Gas Test | 12/9/2021 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 12/9/2021 | Approved | JESUS PINEDA |
| Sewer | 12/9/2021 | Not Ready for Inspection | JESUS PINEDA |
| Drywall Nailing | 12/10/2021 | Approved | JAVIER RAMOS JR |
| Sewer | 12/10/2021 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/10/2021 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 5/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/24/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/24/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 6/13/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/13/2022 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/13/2022 | Approved | CHRIS CHRISTENSEN |