22633 W CALVERT ST 91367

Certificate Information: 22633 W CALVERT ST 91367

Application / Permit
20010-20000-04336
Plan Check / Job No.
B20VN14754
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (20'-2"x 16'-0") DETACHED REC. ROOM, NFPA-13R FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 6/24/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 TROY DEGUZMAN
Corrections Issued 12/2/2020 TROY DEGUZMAN
Quality Review Completed 12/3/2020 CHON CHIO KUO
Building Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 6/17/2021 TROY DEGUZMAN
Applicant returned to address corrections 6/22/2021 TROY DEGUZMAN
Plan Check Approved 6/24/2021 TROY DEGUZMAN
Issued 6/24/2021 APPLICANT
CofO in Progress 7/13/2022 TROY SANDERS
Permit Finaled 8/3/2022 JOHN JANSON
CofO Issued 8/3/2022 JOHN JANSON
Permit Finaled 8/3/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/11/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 6/17/2021 TROY DEGUZMAN
Green Code Cleared 6/17/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2021 Not Ready for Inspection LILIANA PORTILLO
Special/Order Compliance 7/15/2021 Partial Inspection MICHAEL PELHAM
Underground Mechanical 7/15/2021 Approved LILIANA PORTILLO
Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 8/17/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 10/1/2021 Approved TROY SANDERS
HVAC-Rough 10/21/2021 Approved TROY SANDERS
ELECTRICAL-Rough 11/2/2021 Approved TROY SANDERS
HVAC-Rough 11/2/2021 Approved TROY SANDERS
Shower Pan 11/2/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 11/8/2021 Partial Approval TROY SANDERS
Green Building Rough 11/8/2021 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 11/8/2021 Partial Approval TROY SANDERS
Verify Sprinkler Sign Off 11/8/2021 Not Ready for Inspection TROY SANDERS
Wood Frame 11/8/2021 Approved TROY SANDERS
Insulation 11/15/2021 Approved TROY SANDERS
Interior/Exterior Lathing 11/15/2021 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 11/19/2021 Partial Approval TROY SANDERS
Drywall Nailing 11/29/2021 Approved TROY SANDERS
Green Building Rough 11/29/2021 Approved TROY SANDERS
ELECTRICAL-Final 3/31/2022 Approved TROY SANDERS
HVAC-Final 3/31/2022 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 7/12/2022 Approved TROY SANDERS
Final 7/12/2022 OK to Issue CofO TROY SANDERS
Green Building Final 7/12/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved TROY SANDERS
Service/Power Release 7/12/2022 Approved TROY SANDERS
Smoke Detectors 7/12/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 7/12/2022 Approved TROY SANDERS