20729 W DEER GRASS CT 91326
Certificate Information: 20729 W DEER GRASS CT 91326
- Application / Permit
- 20010-20000-04313
- Plan Check / Job No.
- B20VN14740
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN 651_PLAN 1B_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | DAWN MC NULTY |
| Corrections Issued | 12/28/2020 | DAWN MC NULTY |
| Quality Review Completed | 12/28/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/5/2021 | APPLICANT |
| Applicant returned to address corrections | 5/3/2021 | DAWN MC NULTY |
| Plan Check Approved | 5/10/2021 | DAWN MC NULTY |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 12/20/2022 | HENRY KIM |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/6/2021 | ROBERT DUFF |
| Address approval | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Permit | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2021 | LEE GUILBEAUX |
| "T" removal | Cleared | 4/8/2021 | DENZEL HENDERSON |
| CPC | Cleared | 4/8/2021 | DENZEL HENDERSON |
| Specific Plan | Cleared | 4/8/2021 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 4/8/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/8/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/8/2021 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 4/14/2021 | AMMAR ELTAWIL |
Contact Information
| Architect | Swift,, Daniel R; Lic. No.: C32860 | 4601 WESTOWN PARKWAY SUITE 208 WEST DES MOINES, IA 50266 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 26772 DESERT LOCUST ST MURRIETA, CA 92562 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/3/2022 | Corrections Issued | HENRY KIM |
| Sewer | 2/3/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 2/4/2022 | Not Ready for Inspection | HENRY KIM |
| Underground Mechanical | 2/8/2022 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 2/25/2022 | Approved | HENRY KIM |
| Deputy Reinf. Concrete | 2/28/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 6/7/2022 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 6/22/2022 | Approved | SEAN WIRCH |
| Shower Pan | 6/24/2022 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 7/21/2022 | Approved | HENRY KIM |
| HVAC-Rough | 7/21/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 7/21/2022 | Approved | HENRY KIM |
| Deputy Wood Construction | 7/29/2022 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 8/2/2022 | Corrections Issued | HENRY KIM |
| Green Building Rough | 8/2/2022 | Not Ready for Inspection | HENRY KIM |
| Verify Sprinkler Sign Off | 8/2/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 9/1/2022 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Partial Approval | HENRY KIM |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | HENRY KIM |
| Green Building Rough | 9/8/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/8/2022 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 9/16/2022 | Partial Approval | HENRY KIM |
| Insulation | 9/20/2022 | Approved | HENRY KIM |
| Drywall Nailing | 9/29/2022 | Approved | HENRY KIM |
| Smoke Detectors | 9/29/2022 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 10/4/2022 | Approved | HENRY KIM |
| Underground Mechanical | 11/1/2022 | Approved | HENRY KIM |
| Gas Test | 11/3/2022 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 11/4/2022 | Not Ready for Inspection | HENRY KIM |
| Service/Power Release | 11/10/2022 | Not Ready for Inspection | HENRY KIM |
| Service/Power Release | 11/15/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/8/2022 | Corrections Issued | HENRY KIM |
| HVAC-Final | 12/8/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 12/8/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/15/2022 | Corrections Issued | HENRY KIM |
| Final | 12/15/2022 | Corrections Issued | HENRY KIM |
| Green Building Final | 12/15/2022 | Approved | HENRY KIM |
| HVAC-Final | 12/15/2022 | Approved | HENRY KIM |
| Smoke Detectors | 12/15/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/19/2022 | Approved | HENRY KIM |
| Final | 12/19/2022 | OK to Issue CofO | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | HENRY KIM |