17550 W MAGNOLIA BLVD 91316

Certificate Information: 17550 W MAGNOLIA BLVD 91316

Application / Permit
20010-20000-04280
Plan Check / Job No.
B20VN14687
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 20'-8" x 25'-8" ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
Issued on 6/7/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 SEAN SHAHMIRI
Corrections Issued 11/22/2020 SEAN SHAHMIRI
Quality Review Completed 11/24/2020 OMID HEDAYAT
Building Plans Picked Up 11/24/2020 APPLICANT
Applicant returned to address corrections 5/4/2021 SEAN SHAHMIRI
Applicant returned to address corrections 5/14/2021 SEAN SHAHMIRI
Applicant returned to address corrections 6/7/2021 SEAN SHAHMIRI
Plan Check Approved 6/7/2021 SEAN SHAHMIRI
Issued 6/7/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/22/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/26/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/26/2021 JOHN TRIANTAFYLLOS
ZI Cleared 1/26/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 5/12/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/27/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 6/3/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/14/2021 Partial Inspection STEVEN BACK
PLUMBING-Rough 6/29/2021 Partial Approval STEVEN BACK
Pre-Inspection 6/29/2021 Partial Inspection STEVEN BACK
Sewer 6/29/2021 Approved STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/2/2021 Approved STEVEN BACK
Footing/Foundation/Slab 7/2/2021 Approved STEVEN BACK
Pre-Inspection 7/2/2021 Corrections Issued STEVEN BACK
Underground Mechanical 7/2/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved RONALD COWAN
ELECTRICAL-Rough 7/19/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 7/19/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 7/19/2021 Approved STEVEN BACK
ELECTRICAL-Rough 7/23/2021 Approved STEVEN BACK
HVAC-Final 7/23/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 7/26/2021 Conditional Approval RONALD COWAN
Green Building Rough 7/26/2021 Approved RONALD COWAN
Shower Pan 7/26/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 7/30/2021 Approved STEVEN BACK
Insulation 7/30/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 7/30/2021 Approved STEVEN BACK
Drywall Nailing 8/3/2021 Approved STEVEN BACK
Final 10/19/2021 Corrections Issued SEAN HAUPT
Green Building Final 10/19/2021 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved SEAN HAUPT
Service/Power Release 10/19/2021 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 10/19/2021 Approved SEAN HAUPT
Final 10/26/2021 Conditional Approval SEAN HAUPT
Green Building Final 10/26/2021 Approved SEAN HAUPT
Service/Power Release 10/26/2021 Approved SEAN HAUPT
Final 1/20/2022 Corrections Issued SEAN HAUPT