17550 W MAGNOLIA BLVD 91316
Certificate Information: 17550 W MAGNOLIA BLVD 91316
- Application / Permit
- 20010-20000-04280
- Plan Check / Job No.
- B20VN14687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 20'-8" x 25'-8" ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- Issued on 6/7/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | SEAN SHAHMIRI |
| Corrections Issued | 11/22/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/24/2020 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/14/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/7/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/7/2021 | SEAN SHAHMIRI |
| Issued | 6/7/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/26/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 1/26/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 5/12/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/27/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/3/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2021 | Partial Inspection | STEVEN BACK |
| PLUMBING-Rough | 6/29/2021 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 6/29/2021 | Partial Inspection | STEVEN BACK |
| Sewer | 6/29/2021 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/2/2021 | Approved | STEVEN BACK |
| Pre-Inspection | 7/2/2021 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 7/2/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 7/19/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 7/19/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/19/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/23/2021 | Approved | STEVEN BACK |
| HVAC-Final | 7/23/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/26/2021 | Conditional Approval | RONALD COWAN |
| Green Building Rough | 7/26/2021 | Approved | RONALD COWAN |
| Shower Pan | 7/26/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 7/30/2021 | Approved | STEVEN BACK |
| Insulation | 7/30/2021 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 7/30/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 8/3/2021 | Approved | STEVEN BACK |
| Final | 10/19/2021 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 10/19/2021 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 10/19/2021 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 10/19/2021 | Approved | SEAN HAUPT |
| Final | 10/26/2021 | Conditional Approval | SEAN HAUPT |
| Green Building Final | 10/26/2021 | Approved | SEAN HAUPT |
| Service/Power Release | 10/26/2021 | Approved | SEAN HAUPT |
| Final | 1/20/2022 | Corrections Issued | SEAN HAUPT |