13453 W MARGATE ST 91401
Certificate Information: 13453 W MARGATE ST 91401
- Application / Permit
- 20010-20000-04279
- Plan Check / Job No.
- B20VN14685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 15'3" X 15' DETACHED RECREATION ROOM , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | RARES BODEA |
| Corrections Issued | 12/24/2020 | RARES BODEA |
| Quality Review Completed | 12/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
| Applicant returned to address corrections | 6/15/2021 | RARES BODEA |
| Plan Check Approved | 6/29/2021 | RARES BODEA |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | MISAEL ESPARZA |
| Permit Finaled | 6/14/2022 | MICHAEL SMITH |
| CofO Issued | 6/14/2022 | MICHAEL SMITH |
| Permit Finaled | 6/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/20/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/24/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/7/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 9/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 9/21/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/21/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/24/2021 | Conditional Approval | GORDON ZUBER |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/1/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/1/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/8/2021 | Approved | MISAEL ESPARZA |
| Insulation | 12/21/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 1/10/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/10/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/17/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 5/17/2022 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 5/17/2022 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/26/2022 | Conditional Approval | MISAEL ESPARZA |
| Final | 5/26/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/26/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 5/26/2022 | Not Required | MISAEL ESPARZA |
| Smoke Detectors | 5/26/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 6/10/2022 | Approved | MISAEL ESPARZA |
| Final | 6/10/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 6/10/2022 | Approved | MISAEL ESPARZA |