12462 S WOODLEY AVE 91344
Certificate Information: 12462 S WOODLEY AVE 91344
- Application / Permit
- 20010-20000-04274
- Plan Check / Job No.
- B20VN14657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT ( 36'-5"X33'-9") PER LAMC 12.22 A.33(c) and (d), all work per WFPP
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 12/14/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 12/31/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/5/2021 | APPLICANT |
| Applicant returned to address corrections | 10/8/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/8/2021 | JON BLAINE |
| Issued | 11/8/2021 | APPLICANT |
| CofO in Progress | 1/18/2023 | JAVIER RAMOS JR |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 1/11/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/2/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 3/5/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/23/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/16/2021 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 10/12/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 11/3/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/17/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 12/27/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 3/7/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 3/7/2022 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Approved | MICHAEL TEMPLE |
| Gas Test | 3/7/2022 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 3/7/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 3/7/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/7/2022 | Partial Approval | MICHAEL TEMPLE |
| Sewer | 3/7/2022 | Approved | MICHAEL TEMPLE |
| Underground Mechanical | 3/7/2022 | Corrections Issued | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 3/7/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Wood Frame | 3/7/2022 | Approved | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/14/2022 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Rough | 3/14/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/14/2022 | Approved | MICHAEL TEMPLE |
| Underground Mechanical | 3/14/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 3/24/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/6/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/2/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/2/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/29/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 11/29/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 11/29/2022 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/29/2022 | Approved | JAVIER RAMOS JR |