4909 E ALDAMA ST 90042
Certificate Information: 4909 E ALDAMA ST 90042
- Application / Permit
- 20010-20000-04267
- Plan Check / Job No.
- B20VN14619
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 story (24' x 42 ') ACCESSORY DWELLING UNIT/ with 8' x 5' PORCH PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | CHON CHIO KUO |
| Corrections Issued | 12/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
| Quality Review Completed | 4/21/2022 | STEVEN KIM |
| Plan Check Approved | 4/21/2022 | MOHAMMAD ESMAILI |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 4/21/2023 | OSVALDO PARAMO |
| CofO in Progress | 4/21/2023 | OSVALDO PARAMO |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
| CofO Issued | 4/30/2023 | DEROLD HAUFF |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 4/26/2021 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 5/26/2021 | NASHYA JENSEN |
| ZI | Cleared | 5/26/2021 | NASHYA JENSEN |
| BHO/Hillside ordinance | Cleared | 9/13/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 11/24/2021 | RUEL COLE |
| Sewer availability | Cleared | 12/30/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 1/13/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/13/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 3/14/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | THAN WIN |
| GPI Written Notices | Cleared | 4/21/2022 | CHON CHIO KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2022 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/11/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 7/27/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/7/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 9/7/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 9/7/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/12/2022 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 9/12/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 9/12/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 9/15/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/15/2022 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/15/2022 | Approved | OSVALDO PARAMO |
| Insulation | 9/20/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/26/2022 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 12/13/2022 | Partial Approval | OSVALDO PARAMO |
| Sewer | 1/9/2023 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 1/12/2023 | Partial Approval | OSVALDO PARAMO |
| Final | 2/14/2023 | No Access for Inspection | OSVALDO PARAMO |
| Green Building Final | 2/14/2023 | No Access for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 2/14/2023 | No Access for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 2/14/2023 | No Access for Inspection | OSVALDO PARAMO |
| Final | 2/22/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 2/22/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 2/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 2/22/2023 | Approved | OSVALDO PARAMO |
| Final | 3/1/2023 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 3/1/2023 | Approved | OSVALDO PARAMO |
| Final | 4/17/2023 | Partial Inspection | RUBEN SALAS |
| Final | 4/21/2023 | OK to Issue CofO | OSVALDO PARAMO |