3454 S MOORE ST 90066

Certificate Information: 3454 S MOORE ST 90066

Application / Permit
20010-20000-04266
Plan Check / Job No.
B20VN14615
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 33'-6" x 27'-6" TWO STORY DETACHED A.D.U WITH ATTACHED TWO CAR GARAGE PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
CofO Issued on 9/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 SARKIS HARABEDIAN
Corrections Issued 12/12/2020 SARKIS HARABEDIAN
Quality Review Completed 12/18/2020 STEVEN KIM
Building Plans Picked Up 12/21/2020 APPLICANT
Plan Check Approved 4/6/2021 PETER MOSESIAN
Issued 4/6/2021 APPLICANT
CofO in Progress 8/31/2022 JESUS RODRIGUEZ
Permit Finaled 9/1/2022 DANIEL ORRANTE
CofO Issued 9/1/2022 DANIEL ORRANTE
Permit Finaled 9/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/7/2021 DINAH GARIN
Sewer availability Cleared 1/8/2021 DINAH GARIN
Hydrant and Access approval Cleared 2/9/2021 JEREMY CARTER
Low Impact Development Cleared 3/24/2021 ANDRES COVARRUBIAS
GPI Written Notices Cleared 3/26/2021 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 3/26/2021 SARKIS HARABEDIAN
Roof/Waste drainage to street Cleared 3/26/2021 DINAH GARIN
Specific Plan Cleared 4/6/2021 WESTON PRINGLE

Contact Information

Contractor Anderson Robert Construction; Lic. No.: 861662-B 18169 KNOLL HILL      GRANADA HILLS, CA 91344
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/8/2021 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 4/14/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 8/23/2021 Approved JUAN VALENZUELA
Sewer 8/23/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Deputy Drilled-In Anchors 8/27/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 8/27/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Corrections Issued ENRIQUE MIRELES
Green Building Rough 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/27/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 9/29/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 9/29/2021 Approved ENRIQUE MIRELES
Green Building Rough 9/29/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 9/29/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Conditional Approval RICHARD STEINBACH
HVAC-Rough 10/15/2021 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 10/15/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 10/15/2021 Approved ENRIQUE MIRELES
HVAC-Rough 10/18/2021 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 10/18/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/20/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Approved ENRIQUE MIRELES
HVAC-Rough 10/20/2021 Approved ENRIQUE MIRELES
Special/Order Compliance 10/20/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 10/20/2021 Approved ENRIQUE MIRELES
Drywall Nailing 10/27/2021 Approved ENRIQUE MIRELES
Insulation 10/27/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/8/2021 Approved JOHN KAYON
Gas Test 12/10/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/10/2021 Approved STEPHANIE SWANSON
Shower Pan 12/10/2021 Approved STEPHANIE SWANSON
Final 4/12/2022 Not Ready for Inspection PATRICK QUALEY
Green Building Final 4/12/2022 Not Ready for Inspection PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/12/2022 SGSOV Not Ready PATRICK QUALEY
Service/Power Release 4/12/2022 Not Ready for Inspection PATRICK QUALEY
Smoke Detectors 4/12/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 6/1/2022 Approved PATRICK QUALEY
PLUMBING-Final 6/1/2022 Corrections Issued PATRICK QUALEY
Service/Power Release 6/1/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 6/13/2022 Approved PATRICK QUALEY
PLUMBING-Final 6/13/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 6/17/2022 Approved PATRICK QUALEY
Final 6/17/2022 Corrections Issued PATRICK QUALEY
Green Building Final 6/17/2022 Approved PATRICK QUALEY
PLUMBING-Final 6/17/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Ready PATRICK QUALEY
Service/Power Release 6/17/2022 Not Ready for Inspection PATRICK QUALEY
Smoke Detectors 6/17/2022 Approved PATRICK QUALEY
Final 6/27/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 6/27/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Approved PATRICK QUALEY
Service/Power Release 6/27/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 8/15/2022 Approved BOBBY KEY
Final 8/15/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 8/15/2022 Approved BOBBY KEY
PLUMBING-Final 8/15/2022 Approved BOBBY KEY
Service/Power Release 8/15/2022 Not Ready for Inspection BOBBY KEY
Final 8/16/2022 Corrections Issued BOBBY KEY
Final 8/30/2022 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 8/30/2022 Approved JESUS RODRIGUEZ