20813 W BRYANT ST 91306

Certificate Information: 20813 W BRYANT ST 91306

Application / Permit
20010-20000-04265
Plan Check / Job No.
B20VN14614
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'X 30' TWO-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING. INVESTIGATION FEES ARE A MINIMUM $400.00 OR DOUBLE THE PERMIT FEE WHICHEVER IS GREATER. See LAMC Section 91.107.5.1. Payment of investigation fees due at time of permit issuance.
Permit Issued
Issued on 7/8/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 PARISA ZAHABI
Corrections Issued 12/12/2020 PARISA ZAHABI
Quality Review Completed 12/17/2020 OMID HEDAYAT
Applicant returned to address corrections 6/4/2021 PARISA ZAHABI
Plan Check Approved 6/21/2021 PARISA ZAHABI
No Progress 6/21/2021 PARISA ZAHABI
Plan Check Approved 6/23/2021 PARISA ZAHABI
Building Plans Picked Up 6/25/2021 APPLICANT
Issued 7/8/2021 APPLICANT
CofO in Progress 8/25/2022 CHRIS CHRISTENSEN
Permit Finaled 8/25/2022 JOHN JANSON
CofO Issued 8/25/2022 JOHN JANSON
Permit Finaled 8/25/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/11/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/11/2021 ADRIAN CASTRO
Sewer availability Cleared 2/8/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/10/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/12/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/2/2021 CARLOS AGUILERA
Zoning Information File Cleared 6/4/2021 PARISA ZAHABI

Contact Information

Contractor South Pacific Development Construction Inc; Lic. No.: 1063751-B 14926 TOUCHWOOD AVE      BELLFLOWER, CA 90706
Engineer Bui,, Mai Phuong; Lic. No.: C61280 7445 LURLINE AVE      WINNETKA, CA 91306

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/16/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 7/16/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 7/16/2021 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 7/26/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 7/26/2021 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 8/18/2021 Approved DAVID STEPANYAN
Pre-Inspection 8/18/2021 Partial Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 10/21/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 10/21/2021 Approved DAVID STEPANYAN
Green Building Rough 10/21/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 10/21/2021 Approved DAVID STEPANYAN
Green Building Rough 11/1/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 11/1/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 1/6/2022 Approved DAVID SCANTLIN
Green Building Rough 1/6/2022 Approved DAVID SCANTLIN
HVAC-Rough 1/6/2022 Approved DAVID SCANTLIN
Insulation 1/12/2022 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 1/12/2022 Partial Approval JUSTIN HAWLEY
Drywall Nailing 1/18/2022 Approved JUSTIN HAWLEY
Final 5/10/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/10/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 5/10/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 5/10/2022 Corrections Issued CHRIS CHRISTENSEN
Final 7/8/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 7/8/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 7/8/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 7/8/2022 Approved CHRIS CHRISTENSEN