8005 N WAKEFIELD AVE 91402
Certificate Information: 8005 N WAKEFIELD AVE 91402
- Application / Permit
- 20010-20000-04263
- Plan Check / Job No.
- B20VN14609
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' x 39' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/15/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
| Plan Check Approved | 9/21/2021 | SELLA BENYAMIN |
| Issued | 9/21/2021 | APPLICANT |
| CofO in Progress | 6/14/2023 | DAVID MATSON |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
| CofO Issued | 6/15/2023 | MICHAEL SMITH |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/31/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 6/3/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/6/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/26/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/26/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2021 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 11/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/8/2021 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 12/8/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/13/2021 | Approved | GREGG CUMMINGS |
| Sewer | 12/13/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 12/13/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/15/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/15/2022 | Corrections Issued | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/1/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/1/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/1/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 3/1/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 3/1/2022 | Approved | GREGG CUMMINGS |
| Insulation | 3/9/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/21/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/21/2022 | Approved | WILLIAM WREN |
| Shower Pan | 3/21/2022 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 3/31/2022 | Partial Approval | GREGG CUMMINGS |
| Final | 7/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 7/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 7/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 7/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 7/14/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 7/14/2022 | Approved | GREGG CUMMINGS |
| Final | 8/29/2022 | Conditional Approval | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/6/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Service/Power Release | 9/6/2022 | Approved | DEANDRE HOFFMAN |
| Final | 6/14/2023 | OK to Issue CofO | DAVID MATSON |