27532 S SIENA DR 90732

Certificate Information: 27532 S SIENA DR 90732

Application / Permit
20010-20000-04218
Plan Check / Job No.
B20VN14498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(TR 71866-01 PVSP-SUBAREA 2) PROPOSE TWO STORY SFD WITH ATTACHED GARAGE_PLAN 3C_ [BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D].
Permit Issued
Issued on 2/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 DAWN MC NULTY
Corrections Issued 12/28/2020 DAWN MC NULTY
Quality Review Completed 1/5/2021 CHON CHIO KUO
Building Plans Picked Up 1/7/2021 APPLICANT
Applicant returned to address corrections 2/25/2021 DAWN MC NULTY
Applicant returned to address corrections 2/26/2021 DAWN MC NULTY
Plan Check Approved 11/15/2021 DAWN MC NULTY
Issued 2/1/2022 APPLICANT
CofO in Progress 11/9/2022 ANSON MAGLASANG
Permit Finaled 11/12/2022 DEROLD HAUFF
CofO Issued 11/12/2022 DEROLD HAUFF
Permit Finaled 11/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Private street Cleared 1/8/2021 PAUL CAPORASO
Tract Map conditions Cleared 1/8/2021 PAUL CAPORASO
Tract Map conditions Cleared 1/8/2021 PAUL CAPORASO
Low Impact Development Cleared 1/21/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 1/29/2021 ROBERT DUFF
CPC Cleared 2/2/2021 ANACANY HURTADO
CPC Cleared 2/2/2021 ANACANY HURTADO
CPC Cleared 2/2/2021 ANACANY HURTADO
CPC Cleared 2/2/2021 ANACANY HURTADO
Frnt yard landscape/Water mgmt Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 2/2/2021 ANACANY HURTADO
Specific Plan Cleared 2/2/2021 ANACANY HURTADO
ZA Case Cleared 2/2/2021 ANACANY HURTADO
Miscellaneous Cleared 4/28/2021 JASON CHAN
Address approval Cleared 8/13/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/13/2021 ANTHONY MAINEZ
Highway dedication Cleared 8/13/2021 ANTHONY MAINEZ
Permit Cleared 8/13/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 8/13/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/28/2021 ANTHONY MAINEZ

Contact Information

Architect Kough,, Eric R; Lic. No.: C26497 2539 FAIRWAY DRIVE      COSTA MESA, CA 92627
Contractor Kb Home Coastal Inc; Lic. No.: 630879-B 10990 WILSHIRE BLVD SUITE 700   LEGAL DEPT    LOS ANGELES, CA 90024
Engineer Binatli,, Aret; Lic. No.: C64448 400 SAN FERNANDO MISSION BLVD 200      SAN FERNANDO, CA 91340
Engineer Van, Gaale, Mark Allan; Lic. No.: C58680 185 W ORANGEWOOD AVE SUITE 200      ORANGE, CA 92868

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/8/2022 Partial Approval ANSON MAGLASANG
Underground Mechanical 4/8/2022 Partial Approval ANSON MAGLASANG
Deputy Reinf. Concrete 4/25/2022 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 4/26/2022 Approved ANSON MAGLASANG
Deputy Reinf. Concrete 5/2/2022 Conditional Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 6/27/2022 Not Ready for Inspection ANSON MAGLASANG
HVAC-Rough 6/27/2022 Approved ANSON MAGLASANG
PLUMBING-Rough 6/27/2022 Partial Approval ANSON MAGLASANG
Wood Frame 6/27/2022 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 7/13/2022 Approved ANSON MAGLASANG
Insulation 7/13/2022 Not Ready for Inspection ANSON MAGLASANG
Drywall Nailing 7/22/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 7/25/2022 Approved ANSON MAGLASANG
Drywall Nailing 7/25/2022 Approved ANSON MAGLASANG
Green Building Rough 7/25/2022 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 7/25/2022 Approved ANSON MAGLASANG
Verify Sprinkler Sign Off 7/25/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 8/17/2022 Partial Approval ANSON MAGLASANG
Service/Power Release 10/3/2022 Approved ANSON MAGLASANG
Final 11/1/2022 Not Ready for Inspection ANSON MAGLASANG
Green Building Final 11/1/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 11/1/2022 Not Ready for Inspection ANSON MAGLASANG
Final 11/9/2022 OK to Issue CofO ANSON MAGLASANG
Smoke Detectors 11/9/2022 Approved ANSON MAGLASANG