4930 N PALOMAR DR 91356

Certificate Information: 4930 N PALOMAR DR 91356

Application / Permit
20010-20000-04082
Plan Check / Job No.
B20VN14263
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 82'-11" x 91'-2" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 3-CAR GARAGE. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO in Progress on 5/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 SEAN SHAHMIRI
Corrections Issued 11/13/2020 SEAN SHAHMIRI
Quality Review Completed 11/13/2020 OMID HEDAYAT
Building Plans Picked Up 11/18/2020 APPLICANT
Applicant returned to address corrections 6/18/2021 SEAN SHAHMIRI
Applicant returned to address corrections 8/3/2021 SEAN SHAHMIRI
Applicant returned to address corrections 10/29/2021 SEAN SHAHMIRI
Plan Check Approved 12/21/2021 SEAN SHAHMIRI
Issued 1/13/2022 APPLICANT
CofO in Progress 5/5/2025 JOHN KIDWELL
CofO in Progress 1/5/2026 JOHN KIDWELL

Permit Application Clearance Information

Address approval Cleared 12/1/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 12/1/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 12/1/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 12/1/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 12/1/2020 GUILLERMO PETRA
Permit Cleared 12/1/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/2/2020 GUILLERMO PETRA
Sewer availability Cleared 12/2/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Trees in Parkway Cleared 3/31/2021 JOHN KIM
ZI Cleared 4/12/2021 MIGUEL GAMBOA
Watercourse Cleared 5/4/2021 GUILLERMO PETRA
Low Impact Development Cleared 6/9/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/17/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 6/18/2021 SEAN SHAHMIRI
Miscellaneous Cleared 11/4/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Rubeiz,, Nadim Michel; Lic. No.: C69454 22711 CALIFA ST      WOODLAND HILLS, CA 91367
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 3/18/2022 Approved DAVID SANDOVAL
Sewer 3/18/2022 Approved DAVID SANDOVAL
Underground Mechanical 3/18/2022 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 3/21/2022 Approved DAVID SANDOVAL
Deputy Steel/Welding 3/24/2022 Partial Approval ROBERT GOLD
Deputy Steel/Welding 4/4/2022 Conditional Approval DAVID SANDOVAL
Deputy Steel/Welding 5/2/2022 Conditional Approval DAVID SANDOVAL
Deputy Steel/Welding 5/10/2022 Conditional Approval MORRIS JACKSON
Deputy Steel/Welding 5/11/2022 Conditional Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Partial Approval DAVID SANDOVAL
Deputy Steel/Welding 5/24/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/3/2022 Not Ready for Inspection JEFFREY BULL
Green Building Rough 10/3/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 10/3/2022 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 12/14/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 12/14/2022 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 12/14/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 12/14/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 1/4/2023 Partial Approval DAVID SANDOVAL
Insulation 1/13/2023 Corrections Issued JESUS PINEDA
Drywall Nailing 2/3/2023 Approved DAVID SANDOVAL
Shower Pan 2/14/2023 Approved DAVID SANDOVAL
Interior/Exterior Lathing 2/23/2023 Approved DAVID SANDOVAL
Service/Power Release 7/17/2024 Corrections Issued JOHN KIDWELL
Service/Power Release 7/26/2024 Not Ready for Inspection MORRIS JACKSON
Service/Power Release 8/2/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 10/23/2024 Approved JOHN KIDWELL
Final 10/23/2024 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 10/23/2024 Approved JOHN KIDWELL
Green Building Final 10/23/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 10/23/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/23/2024 Approved JOHN KIDWELL
Green Building Final 11/6/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Not Ready JOHN KIDWELL
Final 12/9/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 12/9/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Approved JOHN KIDWELL
Final 4/7/2025 Corrections Issued JOHN KIDWELL
Green Building Final 4/7/2025 Approved JOHN KIDWELL
Final 4/24/2025 Not Ready for Inspection JOHN KIDWELL
Special/Order Compliance 1/6/2026 Corrections Issued JOHN KIDWELL
Final 1/14/2026 Partial Inspection JOHN KIDWELL