16759 W RAYEN ST 91343

Certificate Information: 16759 W RAYEN ST 91343

Application / Permit
20010-20000-04081
Plan Check / Job No.
B20VN14258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (72'-4"x61'-6") W/ ATT. GARAGE FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 7/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 MOHAMMAD ESMAILI
Corrections Issued 12/8/2020 MOHAMMAD ESMAILI
Quality Review Completed 1/7/2021 OMID HEDAYAT
Building Plans Picked Up 1/13/2021 APPLICANT
Applicant returned to address corrections 9/1/2021 MOHAMMAD ESMAILI
Plan Check Approved 9/20/2021 MOHAMMAD ESMAILI
Issued 9/28/2021 APPLICANT
CofO in Progress 7/11/2025 JOAQUIN GREENOUGH
Permit Finaled 7/11/2025 RUBEN SALAS
CofO Issued 7/11/2025 RUBEN SALAS
Permit Finaled 7/11/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 1/11/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/12/2021 ADRIAN CASTRO
Sewer availability Cleared 1/12/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG
Miscellaneous Cleared 3/1/2021 PABLO ESTRADA
Disturb/Remove Protected Trees Cleared 5/24/2021 MOHAMMAD ESMAILI
Low Impact Development Cleared 8/5/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/10/2021 CARLOS AGUILERA

Contact Information

Contractor Grid Line Structures Inc; Lic. No.: 1070999-B 5304 1/2 LA MIRADA AVE      LOS ANGELES, CA 90029
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 11/29/2021 Partial Approval RAUL OLAGI
Masonry Wall/Backfill 12/15/2021 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 12/15/2021 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 12/15/2021 Not Ready for Inspection RAUL OLAGI
Masonry Wall/Backfill 12/21/2021 Partial Inspection JESUS PINEDA
PLUMBING-Rough 12/21/2021 Partial Approval JESUS PINEDA
Underground Mechanical 12/21/2021 Partial Approval JESUS PINEDA
Masonry Wall/Backfill 1/13/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 1/13/2022 Corrections Issued RAUL OLAGI
Masonry Wall/Backfill 2/11/2022 Approved RICHARD DOCKUS
Underground Mechanical 2/11/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 2/25/2022 Partial Approval RAUL OLAGI
Underground Mechanical 2/25/2022 Partial Approval RAUL OLAGI
Underground Mechanical 3/3/2022 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/7/2022 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/11/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 8/4/2022 Approved RAUL OLAGI
Pre-Inspection 8/10/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Corrections Issued RAUL OLAGI
Deputy Wood Construction 10/17/2022 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 11/29/2022 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 12/16/2022 Partial Approval RAUL OLAGI
HVAC-Rough 3/7/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 3/16/2023 Approved RAUL OLAGI
Insulation 4/3/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/14/2023 Approved RAUL OLAGI
Green Building Rough 4/14/2023 Approved RAUL OLAGI
Insulation 4/14/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 4/14/2023 Approved RAUL OLAGI
Drywall Nailing 4/18/2023 Approved RAUL OLAGI
Shower Pan 5/22/2023 Corrections Issued RAUL OLAGI
Shower Pan 5/24/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 6/1/2023 Approved RAUL OLAGI
Shower Pan 6/1/2023 Corrections Issued RAUL OLAGI
Shower Pan 6/14/2023 Approved RAUL OLAGI
Sewer 7/24/2023 Approved RAUL OLAGI
Underground Mechanical 7/24/2023 Approved RAUL OLAGI
ELECTRICAL-Final 12/18/2024 Approved GAREN HAYRAPETYAN
Gas Test 12/18/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Final 12/18/2024 Approved GAREN HAYRAPETYAN
Smoke Detectors 12/18/2024 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 1/24/2025 Approved GAREN HAYRAPETYAN
Smoke Detectors 1/24/2025 Approved GAREN HAYRAPETYAN
Pre-Inspection 4/8/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 5/7/2025 Approved SALVADOR MARTINEZ
Service/Power Release 5/7/2025 Approved SALVADOR MARTINEZ
Final 6/26/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 6/26/2025 Approved SALVADOR MARTINEZ
Green Building Final 6/26/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved SALVADOR MARTINEZ
Final 7/10/2025 OK to Issue CofO JOAQUIN GREENOUGH