19534 W VOSE ST 91335

Certificate Information: 19534 W VOSE ST 91335

Application / Permit
20010-20000-04062
Plan Check / Job No.
B20VN14235
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 7/17/2021
Issuing Office
Current Status
CofO Issued on 3/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/9/2020 RAPHAEL ROSAS
Corrections Issued 11/11/2020 RAPHAEL ROSAS
Issued 7/17/2021 APPLICANT
Building Plans Picked Up 7/19/2021 APPLICANT
CofO in Progress 1/20/2022 VINCENT HANLEY
Permit Finaled 3/29/2022 JOHN JANSON
CofO Issued 3/29/2022 JOHN JANSON
Permit Finaled 3/29/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/25/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/3/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/3/2020 JOHN TRIANTAFYLLOS
ZI Cleared 12/23/2020 LAUREN PADICK
Construction near power lines Cleared 4/19/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/23/2021 ROBERT DUFF
Low Impact Development Cleared 6/7/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/30/2021 GABRIEL ROBLES

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/5/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 8/9/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/24/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 8/24/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval DAVID SANDOVAL
Green Building Rough 8/24/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 8/24/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/24/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Approved PETER FOLLING
HVAC-Rough 8/31/2021 Approved PETER FOLLING
Wood Frame 8/31/2021 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 9/3/2021 Partial Approval VINCENT HANLEY
Green Building Rough 9/3/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/3/2021 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 9/3/2021 Not Ready for Inspection VINCENT HANLEY
Insulation 9/9/2021 Approved KRISTEN CAUSEY
Drywall Nailing 9/14/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/14/2021 Approved VINCENT HANLEY
Sewer 10/15/2021 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 10/15/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/14/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 1/14/2022 Corrections Issued VINCENT HANLEY
Final 1/14/2022 Corrections Issued VINCENT HANLEY
Green Building Final 1/14/2022 Approved VINCENT HANLEY
HVAC-Final 1/14/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 1/14/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/14/2022 Approved VINCENT HANLEY
Smoke Detectors 1/14/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/14/2022 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 1/20/2022 Approved VINCENT HANLEY
Final 1/20/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/20/2022 Approved VINCENT HANLEY