9846 N ETIWANDA AVE 91325

Certificate Information: 9846 N ETIWANDA AVE 91325

Application / Permit
20010-20000-04057
Plan Check / Job No.
B20VN14212
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42' X 24'11-1/2" ONE STORY DETACHED ACCESORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E), ALL WORK PER WFPP
Permit Issued
Issued on 2/15/2022
Issuing Office
Current Status
CofO Issued on 7/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 RARES BODEA
Corrections Issued 12/4/2020 RARES BODEA
Quality Review Completed 12/10/2020 STEVEN KIM
Building Plans Picked Up 12/11/2020 APPLICANT
Applicant returned to address corrections 2/10/2022 RARES BODEA
Plan Check Approved 2/15/2022 RARES BODEA
Issued 2/15/2022 APPLICANT
CofO in Progress 5/29/2024 DAVID SCANTLIN
CofO in Progress 6/11/2024 DAVID SCANTLIN
CofO Issued 7/19/2024 JOHN JANSON
Permit Finaled 7/19/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/20/2021 CARLOS AGUILERA
Sewer availability Cleared 8/20/2021 CARLOS AGUILERA
Tract Map conditions Cleared 8/24/2021 DANG NGUYEN
Tract Map conditions Cleared 8/24/2021 DANG NGUYEN
Tract Map conditions Cleared 8/24/2021 DANG NGUYEN
Tract Map conditions Cleared 8/24/2021 DANG NGUYEN
ZA Case Cleared 8/24/2021 DANG NGUYEN
Hydrant and Access approval Cleared 10/12/2021 KURT CORRAL
Low Impact Development Cleared 12/27/2021 SAHIL SHARMA
Roof/Waste drainage to street Cleared 12/28/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/23/2022 Corrections Issued JEFFREY PARD
Excavation/Setback/Form/Re-Bar 6/3/2022 Approved JEFFREY PARD
PLUMBING-Rough 6/3/2022 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 7/8/2022 Partial Approval JEFFREY PARD
Green Building Rough 7/8/2022 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 7/8/2022 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 10/27/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/27/2022 Approved JOHN KIDWELL
Green Building Rough 10/27/2022 Approved JOHN KIDWELL
HVAC-Rough 10/27/2022 Approved JOHN KIDWELL
PLUMBING-Rough 10/27/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/27/2022 Corrections Issued JOHN KIDWELL
Insulation 11/17/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/17/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 12/14/2022 Approved JOHN KIDWELL
Special/Order Compliance 12/14/2022 Partial Inspection MORRIS JACKSON
ELECTRICAL-Rough 4/28/2023 Partial Approval JOHN KIDWELL
PLUMBING-Rough 4/28/2023 Partial Approval JOHN KIDWELL
Service/Power Release 10/17/2023 Not Ready for Inspection DAVID SCANTLIN
Final 3/14/2024 Corrections Issued KRISTEN CAUSEY
Footing/Foundation/Slab 3/14/2024 Approved KRISTEN CAUSEY
Green Building Final 3/14/2024 Approved KRISTEN CAUSEY
HVAC-Final 3/14/2024 Approved KRISTEN CAUSEY
PLUMBING-Final 3/14/2024 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 3/14/2024 Approved KRISTEN CAUSEY
Verify Sprinkler Sign Off 3/14/2024 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 3/29/2024 Approved DAVID SCANTLIN
Final 3/29/2024 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 3/29/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 3/29/2024 Approved DAVID SCANTLIN
Final 5/28/2024 Partial Approval DAVID SCANTLIN
Special/Order Compliance 6/11/2024 Corrections Issued DAVID SCANTLIN