1113 E MARCO PL 90291

Certificate Information: 1113 E MARCO PL 90291

Application / Permit
20010-20000-04021
Plan Check / Job No.
B20VN14128
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 12/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 NILOOFAR MEHRAIN
Corrections Issued 11/4/2020 NILOOFAR MEHRAIN
Quality Review Completed 11/4/2020 CHON CHIO KUO
Building Plans Picked Up 11/4/2020 APPLICANT
Applicant returned to address corrections 2/25/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/12/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/27/2021 NILOOFAR MEHRAIN
Plan Check Approved 5/12/2021 NILOOFAR MEHRAIN
Issued 5/26/2021 APPLICANT
CofO in Progress 12/16/2023 HERBERT GIRON
Permit Finaled 12/18/2023 DANIEL ORRANTE
CofO Issued 12/18/2023 DANIEL ORRANTE
Permit Finaled 12/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/18/2020 DINAH GARIN
Permit Cleared 11/18/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/19/2020 DINAH GARIN
Sewer availability Cleared 11/19/2020 DINAH GARIN
Low Impact Development Cleared 12/10/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/23/2020 DINAH GARIN
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Specific Plan Cleared 1/6/2021 FREDDY GARCIA
Trees in Parkway Cleared 2/8/2021 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/2/2021 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 7/2/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 8/20/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 8/24/2021 Approved JOHNNY MIRANDA
Pre-Inspection 2/24/2022 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 3/24/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 3/24/2022 Not Ready for Inspection STEPHANIE SWANSON
Deputy Wood Construction 4/7/2022 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/22/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 8/22/2022 Not Ready for Inspection DAVID FEILER
Green Building Rough 8/22/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 8/22/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 8/22/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 8/22/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 9/6/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 9/6/2022 Not Ready for Inspection DAVID FEILER
Green Building Rough 9/6/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 9/6/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 9/6/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 10/14/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/14/2022 Corrections Issued DAVID FEILER
Green Building Rough 10/14/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/14/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/14/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 11/7/2022 Partial Approval DAVID FEILER
Deputy Wood Construction 11/7/2022 Approved DAVID FEILER
ELECTRICAL-Rough 11/7/2022 Approved DAVID FEILER
Green Building Rough 11/7/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 11/7/2022 Approved DAVID FEILER
PLUMBING-Rough 11/7/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 11/10/2022 Conditional Approval DAVID FEILER
Green Building Rough 11/10/2022 Approved DAVID FEILER
Shower Pan 11/10/2022 Not Ready for Inspection DAVID FEILER
Insulation 11/15/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 11/15/2022 Not Ready for Inspection DAVID FEILER
Shower Pan 11/15/2022 Approved DAVID FEILER
Insulation 11/16/2022 Approved DAVID FEILER
Drywall Nailing 11/18/2022 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 11/18/2022 Partial Approval CLAYTON GRAHAM
Drywall Nailing 11/22/2022 Approved DAVID FEILER
Gas Test 1/13/2023 Partial Approval DAVID FEILER
Sewer 1/13/2023 Corrections Issued DAVID FEILER
Gas Test 1/20/2023 Partial Approval EVAN COOPER
Sewer 1/20/2023 Approved EVAN COOPER
ELECTRICAL-Final 6/30/2023 No Access for Inspection HERBERT GIRON
Gas Test 7/3/2023 Approved JEREMY TODD
HVAC-Final 7/3/2023 Corrections Issued JEREMY TODD
PLUMBING-Final 7/3/2023 Corrections Issued JEREMY TODD
ELECTRICAL-Final 7/5/2023 Approved EVAN COOPER
HVAC-Final 7/5/2023 Approved EVAN COOPER
PLUMBING-Final 7/5/2023 Approved EVAN COOPER
Special/Order Compliance 7/6/2023 Corrections Issued EVAN COOPER
Service/Power Release 7/21/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 12/5/2023 Approved HERBERT GIRON
Final 12/5/2023 Corrections Issued HERBERT GIRON
Green Building Final 12/5/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 12/5/2023 Approved HERBERT GIRON
Final 12/15/2023 OK to Issue CofO HERBERT GIRON