4363 N LEDGE AVE 91602

Certificate Information: 4363 N LEDGE AVE 91602

Application / Permit
20010-20000-04016
Plan Check / Job No.
B20VN14121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46'-8" X 50'-5" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 SELLA BENYAMIN
Corrections Issued 12/1/2020 SELLA BENYAMIN
Quality Review Completed 12/4/2020 STEVEN KIM
Building Plans Picked Up 12/7/2020 APPLICANT
Plan Check Approved 3/26/2021 SELLA BENYAMIN
Issued 3/26/2021 APPLICANT
CofO in Progress 11/28/2021 THOMAS FINNILA
Permit Finaled 8/2/2022 DANIEL ORRANTE
CofO Issued 8/2/2022 DANIEL ORRANTE
Permit Finaled 8/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 12/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/28/2020 ADRIAN CASTRO
Sewer availability Cleared 12/28/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 1/14/2021 MATTHEW CRAIG
Trees in Parkway Cleared 2/4/2021 JOHN KIM
Low Impact Development Cleared 3/9/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/10/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2021 Partial Inspection ARAM AVEDISIAN
Underground Mechanical 4/6/2021 Approved JOHN HAYES
Footing/Foundation/Slab 4/13/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 No Access for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 5/4/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 5/10/2021 Approved THOMAS FINNILA
HVAC-Rough 5/10/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/19/2021 Approved THOMAS FINNILA
Gas Test 5/19/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/20/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 5/24/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 5/25/2021 Approved JOHN HAYES
Green Building Rough 5/25/2021 Approved JOHN HAYES
HVAC-Rough 5/25/2021 Approved JOHN HAYES
PLUMBING-Rough 5/25/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 5/25/2021 Approved JOHN HAYES
Insulation 6/2/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/2/2021 Approved THOMAS FINNILA
Shower Pan 6/2/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/7/2021 Approved DANIEL ORRANTE
Drywall Nailing 6/9/2021 Approved DANIEL ORRANTE
ELECTRICAL-Final 10/7/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 10/7/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/7/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/12/2021 Approved THOMAS FINNILA
Final 11/15/2021 Partial Inspection THOMAS FINNILA
Green Building Final 11/15/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 11/15/2021 Approved THOMAS FINNILA
Final 11/24/2021 OK to Issue CofO THOMAS FINNILA
Service/Power Release 11/24/2021 Approved THOMAS FINNILA