6368 W 79TH ST 90045

Certificate Information: 6368 W 79TH ST 90045

Application / Permit
20010-20000-03993
Plan Check / Job No.
B20VN14023
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)(g) W/ ATTACHED OPEN LATTICE TRELLIS (NFPA-13D FIRE SPRINLERS THROUGHOUT)
Permit Issued
Issued on 4/19/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 NILOOFAR MEHRAIN
Corrections Issued 11/17/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 3/9/2021 NILOOFAR MEHRAIN
Issued 4/19/2021 APPLICANT
CofO in Progress 8/20/2021 JOHNNY MIRANDA
Permit Finaled 9/8/2021 DEROLD HAUFF
CofO Issued 9/8/2021 DEROLD HAUFF
Permit Finaled 9/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/18/2020 RIDWAN HARDY
Construction within easement Cleared 12/18/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 12/21/2020 MATTHEW CRAIG
Address approval Cleared 1/5/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 1/6/2021 ANTHONY MAINEZ
Sewer availability Cleared 1/6/2021 ANTHONY MAINEZ
Low Impact Development Cleared 2/17/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/24/2021 TRACY TATE
GPI Written Notices Cleared 3/9/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 3/9/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2021 Partial Approval JOHNNY MIRANDA
METHANE-Barrier 5/11/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Subgrade 5/11/2021 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 5/14/2021 Approved JOHNNY MIRANDA
METHANE-Barrier 5/14/2021 Approved JOHNNY MIRANDA
METHANE-Subgrade 5/14/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 5/21/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 5/21/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Corrections Issued PIERRE VEGA
Wood Frame 5/27/2021 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Approved JOHNNY MIRANDA
METHANE-Rough 6/7/2021 Approved JOHNNY MIRANDA
HVAC-Rough 6/14/2021 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 6/14/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 6/16/2021 Partial Approval DONALD GALLAGHER
ELECTRICAL-Rough 6/16/2021 Approved DONALD GALLAGHER
Gas Test 6/16/2021 Approved DONALD GALLAGHER
Interior/Exterior Lathing 6/16/2021 Partial Approval DONALD GALLAGHER
Shower Pan 6/16/2021 Approved DONALD GALLAGHER
Verify Sprinkler Sign Off 6/16/2021 No Access for Inspection DONALD GALLAGHER
Insulation 6/21/2021 Approved DONALD GALLAGHER
Interior/Exterior Lathing 6/21/2021 Approved DONALD GALLAGHER
Drywall Nailing 6/28/2021 Approved AMY COLIN
Interior/Exterior Lathing 6/28/2021 Partial Inspection AMY COLIN
Interior/Exterior Lathing 7/12/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/3/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 8/3/2021 Approved BRENDAN LOONEY
Final 8/3/2021 Corrections Issued BRENDAN LOONEY
Gas Test 8/3/2021 Approved BRENDAN LOONEY
Green Building Final 8/3/2021 Approved BRENDAN LOONEY
Green Building Rough 8/3/2021 Approved BRENDAN LOONEY
HVAC-Final 8/3/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 8/3/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 8/3/2021 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 8/3/2021 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 8/3/2021 Approved BRENDAN LOONEY
Final 8/13/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Final 8/13/2021 Approved JOHNNY MIRANDA
Service/Power Release 8/13/2021 Approved JOHNNY MIRANDA
Final 8/19/2021 OK to Issue CofO JOHNNY MIRANDA