10499 N YOLANDA AVE 91326

Certificate Information: 10499 N YOLANDA AVE 91326

Application / Permit
20010-20000-03992
Plan Check / Job No.
B20VN14016
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-3" x 28'-0" IRREGULAR SHAPED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 SARKIS HARABEDIAN
Corrections Issued 11/21/2020 SARKIS HARABEDIAN
Quality Review Completed 11/30/2020 STEVEN KIM
Plan Check Approved 3/22/2021 SARKIS HARABEDIAN
Issued 3/22/2021 APPLICANT
Building Plans Picked Up 7/15/2022 APPLICANT
CofO in Progress 11/4/2022 DAVID SCANTLIN
Permit Finaled 3/6/2023 DANIEL ORRANTE
CofO Issued 3/6/2023 DANIEL ORRANTE
Permit Finaled 3/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/14/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/14/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/11/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 2/26/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/22/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/17/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 6/23/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Order to Comply Issued JEFFREY PARD
Deputy Wood Construction 8/18/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 9/15/2021 Corrections Issued JEFFREY PARD
PLUMBING-Rough 9/15/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 9/20/2021 Approved STEVEN BACK
Interior/Exterior Lathing 9/20/2021 Partial Approval STEVEN BACK
HVAC-Rough 9/30/2021 Corrections Issued JEFFREY PARD
HVAC-Rough 10/12/2021 Approved JEFFREY PARD
Insulation 10/18/2021 Approved JEFFREY PARD
Drywall Nailing 10/22/2021 Approved JEFFREY PARD
Green Building Rough 10/22/2021 Approved JEFFREY PARD
Gas Test 12/2/2021 Approved JEFFREY PARD
Sewer 2/2/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/4/2022 Approved JEFFREY PARD
Final 3/4/2022 Corrections Issued JEFFREY PARD
Green Building Final 3/4/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Not Ready JEFFREY PARD
Service/Power Release 3/4/2022 Not Required JEFFREY PARD
Smoke Detectors 3/4/2022 Corrections Issued JEFFREY PARD
Verify Sprinkler Sign Off 3/4/2022 Approved JEFFREY PARD
Final 3/17/2022 Not Ready for Inspection JEFFREY PARD
Green Building Final 3/17/2022 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/17/2022 Approved JEFFREY PARD
ELECTRICAL-Final 11/3/2022 Approved DAVID SCANTLIN
Final 11/3/2022 OK to Issue CofO DAVID SCANTLIN
Green Building Final 11/3/2022 Approved DAVID SCANTLIN
HVAC-Final 11/3/2022 Approved DAVID SCANTLIN
PLUMBING-Final 11/3/2022 Approved DAVID SCANTLIN